埃德蒙顿华人社区-Edmonton China

 找回密码
 注册
楼主: playball

[聊天灌水] 加拿大职业工程师考试--一起切磋

[复制链接]
鲜花(0) 鸡蛋(0)
发表于 2008-12-18 22:11 | 显示全部楼层

回复 60楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
能否将您这些题目的答案也公布一下?多谢
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 16:10 | 显示全部楼层
22. Under which of the following project delivery models does the contractor not have significant incentive to reduce costs?
0 ^. ^% l3 h9 M% c : W: C0 j, N) \% N' O
A.     alliance agreement 9 V9 ~9 ?& j* b" h3 j; f( P, @
B.     cost-plus contract
6 |! g+ V4 w$ ^4 @  }2 Y  s' YC.     fixed price contract 4 p) l2 H4 X; e: u3 u
D.     unit price contract
: k3 a0 F( a4 j# u" c8 u
8 [4 n& O6 l& Q% l23. For which of the following types of contract would the scope of work clause be most detailed? 2 {! V, w  x) w, n% f
  
! p7 p) q0 G, [  PA.    unit price
! |3 r4 i( p7 `8 T  v3 D, LB.    fixed price for a design-bid-build project ; d5 l( X4 ^* r+ l
C.    fixed price for a design-build project . g- z* U  h4 F" r9 u9 f' d
D.    cost-plus 7 X- n$ L( K, }7 N+ e9 T+ ]
8 A9 M2 w# \+ U
24. What is another name for an exclusion clause?
7 Y' q1 p% l. o! y. @- Y6 J' c
' \1 D; R. Y3 {A.     escape clause ' Q7 Y3 w0 Q; Z5 _& }
B.    exemption clause ' Z7 X  q! S& z6 |0 z! W5 g
C.    all of the above 0 N- f7 F& z+ J# g9 ?1 S8 k; M
D.    protective clause
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 17:54 | 显示全部楼层

声明

原帖由 Ape 于 2008-12-18 22:11 发表 ( @* w5 n- a% \8 F$ {
能否将您这些题目的答案也公布一下?多谢
' u7 u. \, V! X) s5 m+ q

7 V4 ^) {! f% B+ m1. 本人发帖的目的是为了帮助大家通过NPPE考试, 旨在落实到行动, 把平凡的工作做精做细, 发扬光大下;+ n. G: d7 e) [" h, O
. q6 Q* G0 F- c
2. 总共将有100道考试题目帖上来, 作为大家考前摸底; 如果你不能通过这套题目的话, 你还需要继续努力;# D& p: e2 G, s2 f* L  p& ]
) i8 z; U4 N6 i% s7 Z) S% M: t
3. 答案将在最后被帖上来, 供大家参考.
1 Y5 H! n( b0 y: v! x. l% A/ N& [/ E' S- T
4. 有的同志, 通过了考试拿到了证书的而又在网上大言不惭的, 也可以重新测试下你的水平, 达到从根本上消除你狂妄的口气.
鲜花(0) 鸡蛋(0)
发表于 2008-12-20 00:00 | 显示全部楼层

回复 63楼 的帖子

老杨团队 追求完美
非常感谢,将一直拜读下去,希望早点见到全部。不过上一次结束时是27题,这次怎么又从22题开始了?且内容同前面同题号的题不一样
# F$ q9 W7 B2 Y  [# q6 I9 X, q0 r7 g$ m* t5 [
不要在意别人怎么说,其实通没通过差距不一定很大,可能就在一两分之间,很多刚考完的人出来说心里没底,只等通知了,有一定的运气成分。当然我们还是要好好准备才是。
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 17:47 | 显示全部楼层
对不起, 序号弄错了, 不能改正了. 接着来:
1 P# X  v  {9 u0 p( v% P$ I+ e1 H" d% k$ P2 O
31. Strict liability can be defined as:
3 P- e; Q1 J. b5 M2 O  
; [8 u, w, _4 C% C; o+ `A.    liability flowing from negligence
5 y! T9 Y/ X  r/ Z2 `6 OB.    liability for the fault of another / J' w# X/ f# L* N0 j7 L* J
C    liability without fault
- ?% g, ?8 p" N$ Z, G, ?7 V* {D.    none of the above - [$ ?7 [4 r4 p$ @3 }9 x3 Z5 g1 K1 K5 d
  {) l/ N5 D( B! ~
32. Which of the following is pure economic loss? ! D& ^3 M( [/ ~0 d
4 {, l$ P- T' q
A.      the lost profit of a hotel after the power went out because a motorist knocked over a municipal power pole - a! ?/ R* q6 e; c
B.      the painting repair cost after a roofing contractor carelessly chips the paint on the walls of the house
4 b+ w$ c) o" r$ X( @2 g# fC.      the repair costs after a cyclist's bike is damaged by a careless motorist * @2 A; n1 p. C: X
D.      the medical costs associated with a car accident injury  
. G5 S+ m9 R4 y- n( s9 k: [
' [- [6 B7 A- N* m/ |' C8 R33. Which of the following may succeed as a defence to a negligence claim?
3 R0 {4 m5 X3 j
) m, l: E1 v$ L" }4 i3 C* a3 PA.      the victim is an illegal immigrant
1 z2 a' O0 J) h: ~: S: jB.      the defendant met the standard of care required in the circumstances
1 g( a# a9 R6 _- i& l4 k6 Z! \/ [C.      the tortfeasor did not intend to cause harm to the victim - d0 o- ]# j4 v1 o: T; S0 K1 P( s; }2 y
D.      the victim is far wealthier than the tortfeasor
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 23:09 | 显示全部楼层
34. A third party to a lawsuit may be added by ! k% M5 `  J7 b/ [7 Z/ d" Z

& S9 q7 h$ R$ |8 r- C$ gA. either a plaintiff or a defendant2 B7 g0 x1 [6 s3 N" N9 e" `
B. plaintiff4 q2 I$ A0 W* {4 L
C. defendant3 R% w% S" ^5 D  a) k
D. none of above4 G# d8 E" e' [2 C( ]  E  N
7 ]1 `) c( U3 v" g
35. Limitation periods are defined: 2 F$ v+ E' {7 b2 d5 a
2 c' k; W' s, J$ X$ T, }4 Q
A.      by the courts as part of the common law + q) O& K) ~) z* ?2 \% C7 V/ U! g
B.      only by federal government legislation
/ r! K" B: G9 Q; G' r' i# TC.      only by provincial government legislation * Q3 \" n" t5 V0 s6 e0 M) _
D.      by federal or provincial government legislation, depending on the subject matter of the limitation period
/ z. \) w2 d8 O5 N  k- [- W2 c3 }( H* \, B
36. If a plaintiff was 30 percent responsible for his or her own loss, damages will be reduced by 30 percent. What name is given to the doctrine that imposes this reduction?
/ @( t/ d2 f: q/ O  {     2 w2 e8 K6 o8 |2 B$ w' R, [% B" l/ J
A.     joint liability ! p  z/ ~7 x2 x
B.     joint and several liability ) w2 F# ]  E9 P1 S; R3 q+ n
C.     several liability 6 ?* Z3 t: f" T5 e" Z* [
D.     contributory negligence
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 14:31 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
37. which of the following is not a pleading?
: ~" ^( r+ T3 M, B- g! P; t# \8 s9 {: v' L0 F) k. ^
A. A reply7 U. e* i/ p7 T* P; `2 K
B. A statement of defence
1 m2 W2 z1 J1 c! DC. Discovery of documents, r3 O- \0 e9 a$ B# Q7 L! v
D. Interrogatories
, E% F. `4 B8 q$ Z* v1 y$ W! ^2 e4 w( G; ?$ D4 @
38. What documents do judges examine prior to the commencement of a lawsuit?
& k' |' m$ x# m6 K4 h* o& }% p0 R
% [1 k% T5 S# |" j. h& l5 [A. The statement of claim0 @% t6 A  n% s; G0 ]
B. correspondence between the parties% \; X. a- W9 N2 f( B; u9 a
C. photographs$ C* N7 I1 S5 A  B& W5 o2 ]9 U
D. settlement offers& m4 _4 ]1 }4 @+ Z) ]

" }3 Z; W& e& \39. Which is generally the least voluntary method of dispute resolution?
( m; g. U6 K4 ~* J     6 q2 y: ~, e& Y8 A% u/ e
A.  litigation
5 ]) T8 K/ z4 |' k" P. m& WB.  negotiation ! S$ e4 ]2 F1 g* \( \
C.  mediation
7 R+ m2 q; Q( ]& {D.  arbitration
& A8 s( q$ e, ?! f0 x2 H0 f& r1 c- ?6 ]! `. Y
40. Which of the following methods of dispute resolution offers the advantage of privacy? ( Z% d+ K0 c9 v6 \( I
     
+ a9 j2 ^" D* L% q, j+ S7 K3 C6 uA.  arbitration
4 {7 c& A4 T: h3 f2 cB.  mediation
, f9 e  a4 y# n) _3 ]1 k+ f! iC.  negotiation
/ F+ m6 F! O: Z( W+ S0 o" cD.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 21:05 | 显示全部楼层
41. Which of the following may require further design work by the consultant relatively late in the project? 5 ?$ v7 H2 z6 c8 @# o- _
    . c! h" H: H$ a& r" d
A.  contractor error * n! h* @5 {3 C
B.  tenant requests - _2 \7 a( E) X- }; O6 q* k$ ]
C.  unforeseen conditions
, p$ n2 v4 ?& W) o2 a$ _D.   all of the above ' c; g, Q  V8 h4 u% x+ ?; G$ Z

+ |2 \1 h. K' N3 l) U+ T+ q4 f42. which of the following is not a contractual risk allocation provision?5 w" i% y& {& X3 n

- c, ?) L# v" C/ K$ @6 E7 b8 kA. An insurance clause1 g) ?  ~3 c/ B
B. An 'unforeseen conditions' clause+ G3 L5 w, a  u& k
C. A pay-when-paid clause
$ R0 `0 s" z0 k: J" _D. none of the above
鲜花(0) 鸡蛋(0)
发表于 2008-12-21 23:33 | 显示全部楼层

回复 68楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
感谢。, |- a* P$ c- N' d
这些是以前考过的真题吗?4 n4 ^8 p0 {+ A$ l
请继续
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 11:18 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
43. Which of the following may result in loss of insurance coverage? / C" u+ J% D0 P3 }4 M* R; X6 |
7 {; P( l  S' }. m& Z9 Y1 X0 d
A.      failure to comply with the notice provisions
. u1 p/ @6 O! r( z' UB.      lack of insurable interest ; y- X8 j( y' @/ v" l
C.       all of the above
: d& O& C! g) p1 C3 L& XD.       material non-disclosure
+ y6 ~6 C" u+ _/ B. {
  l; z+ m/ Q' Y44. Which of the following is true?
" @  d8 r- H; {! w
0 q  k! K8 c, I! [9 tA.      professional liability policies are normally claims-made policies
7 b8 _& x9 a- |5 _B.      a claims-made policy covers liability for events that occurred in a specific time period  6 F4 \, M0 C5 h
C.      property insurance policies are either claims-made or occurrence policies
: I* y) |  S8 w% FD.      none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 14:11 | 显示全部楼层
45. which statement is true in the following:
; O* d0 ]0 f" O/ }
2 H+ c" w7 [# F2 H6 o2 F: _A. Sub-subcontractor qualify as a claimant under a standard form CCDC labour and material payment bond;
: W( B# O$ Y7 FB. The limitation periods available to the contractor may not be available to the surety;
& T0 K# ]2 d- z6 B1 D; `7 X* aC. The limitation periods available to the surety may not be available to the principal;" u1 Z9 x& M1 _' @$ u+ O9 r
D. labour and material payment bond is not a one-tier bond.' r+ F! H1 X8 u7 [- U

. z+ M4 u4 J+ s1 N, z; C- U46. Who may be an obligee under a bonding contract?
/ R8 N& K' M* p* I7 |      
0 l5 J7 W1 |" f& H6 Z6 K, JA.  the general contractor
# ?1 \$ T+ t. W1 G5 u6 D4 T0 pB.  a private owner 7 _' l7 ~" F; D
C.  the government
& M# t+ K$ @$ a. ]; LD.  all of the above 0 ^7 Z. T6 z: C5 [5 ]1 b9 O6 u; m
+ m2 S" R+ B9 y
47. A bidder bid $80 and then refused to enter into a contract with the owner. The other three bidders bid $88, $90, and $100. The owner accepted the $90 bid. The face value of the bid bond was $9. How much is the surety required to pay the owner?  1 W) R0 G- ^, k" A
   
  w/ z5 T2 ?; U, v" iA.  $20 # R0 ~8 b9 n( d3 S
B.   $9
( z$ @& T9 P( P: L1 ~# _, B8 ?$ h2 OC.   $8
7 ^! x% h/ m# S6 T6 O! m- nD.   $10
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 09:58 | 显示全部楼层
48. Which parties may be potentially liable for a breach of trust under a Construction Lien Act?
4 w" c3 i' t7 n
9 R$ Q2 r# K1 J1 z5 K% j* ]# uA. Owner
. |2 k  e: _, }/ }5 `' u9 G  nB. contractor9 L( U7 R" `- r3 ~) E
C. worker
1 f: _& J- [& x' \: TD. material supplier# P- s- N! o8 N5 v  n
: z: G1 b$ h0 H: S9 J8 y% I
49. Against what property does the lien holder have a cause of action? 3 n" ^* B$ o6 G& Y+ f. r
        p- c6 z$ N8 d8 U
A.    the interest that the party the lien holder contracted with has in the property on which the work was done
; I1 U$ [" I  F$ k4 T: B( BB.    the property owned by the party the lien holder contracted with   W& c( s3 y5 ~: t" K* f
C.    the property on which the work was done
! y  w# p+ p. k- d% V! UD.    none of the above - r3 C" s0 T2 I0 F7 m- R& }
) W% M& A! c! \
50. An owner providing substitute security for a lien is, in effect:  . u# d" s0 [. Z; Y9 A; f
     
* x, b$ [6 i* O. W% W; d3 tA.  reducing his chances of having to pay out on the lien
5 e% X0 p: q& R1 V: ^# X7 S' OB.  not changing the likelihood of having to pay the lien amount # a9 H; `) C, K* N! q
C.  admitting liability for the lien
  |2 @1 X; J) X# G: rD.  none of the above
大型搬家
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 13:59 | 显示全部楼层
同言同羽 置业良晨
51. What is the key weakness of bar charts as a scheduling tool? # O- ^" B: q0 m- O
      
; ~1 H% E: I. [! ]A.  they are hard to understand
; K" d" n0 `# j: V8 NB.  they take a long time to produce % W% P% o9 R9 `( I) G: I
C.  they do not show an inter-relationship between activities 6 k& X/ @& a8 X
D.  it is often impractical to estimate the time a particular task will take * o/ h; w& O) g8 w
7 M3 _/ ]6 _( g+ e! v
52. Which of the following elements of a delay claim is generally the most difficult to prove?
. Z5 z9 i! a$ W' |7 p3 A      
% Y. ^* M9 t% v) B  ~, I( EA.  the amount of additional cost caused by the delay, or acceleration
+ B, l0 v6 X6 t% ZB.  duty to not interfere with the other party's performance of the contract
4 u) C4 R2 ]8 q9 l' z. J* rC.  breach of the duty to not interfere 0 W2 g9 P4 o( i0 x* y
D.  that the breach of duty caused a delay, or a need for acceleration
- ?+ J2 F1 }# f2 h! h- Y8 v7 b4 z( w. D. f! Y: [6 p5 ~# b
53. Which of the following statement is true in a standard CCDC2 contract?
2 {, q1 J) C# H  p2 ~+ R
( P# U+ V1 N, i  OA. A compensable delay is not excusable, Q3 @0 Q! V" s) j0 L
B. A contractor-caused delay is compensable
% ]. C8 K& y( F1 t7 BC. A contractor-caused delay is not excusable" A' ~! y2 Z% S: p; k% A  A
D. Critical path activities are those in a sequence that must individually be completed before the next activity can begin.
鲜花(0) 鸡蛋(0)
发表于 2008-12-23 21:13 | 显示全部楼层

回复 73楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
good job. a lot of questions for practice laws.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-24 22:35 | 显示全部楼层
54. Which of the following is not true regarding an employer-dependent contractor relationship? " b" j7 H3 s# M3 z3 N( C! E' G& o
      % ]( T, o4 t3 c( E0 z/ \
A.  the contractor may use his or her own tools / e& j9 O; s8 ?& E( w0 H
B.  the contractor is generally not trained by the employer
! @: O) R* j; O) D' QC.  the contractor will generally set his or her own work hours
7 A' s1 t" B! v+ MD.  the contractor is generally economically independent from the employer
- \# p, t7 g8 G7 A7 w1 r1 m" ^; S
55. What term describes the situation in which workers are required to pay union dues but not compelled to join the union? , o9 f9 ^0 f/ |, K9 \
     
$ }9 C( Z2 ^2 N$ t& oA. rand formula
% M! k: V0 W+ _( y6 M) j' _* PB. union shop + W, C# @/ `, p9 {$ |; r
C. closed shop + z+ S) A( I5 ^& w
D. open shop
1 _+ w7 z' ?; h/ [9 `$ n* {2 j$ g
4 W+ ^7 T! h9 i: n56. Which statement is true of an employer under a typical collective agreement?7 A. E) T+ M  h+ t7 M- ?
8 X4 D5 f/ {2 K' K) d+ k" y) S
A. The employer cannot terminate an employee under any circumstances;
# B, F5 d* o( M$ T7 tB. The employer can only terminate an employee if he gives reasonable notice;+ S" Z/ D" S" f0 M9 h) r
C. The employer can not lay off an employee because of a downturn in business;) s% u& d; v9 g" X5 i; Q) w
D. none of the above.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 12:10 | 显示全部楼层
57. Which of the following would likely be confidential information of a contractor, which a construction manager going to a new job should not share with his or her new employer? " g9 j5 y: {2 T5 I5 S, Z. j7 S. D
     
; Y' G" w. f4 [% rA.    the price the contractor pays for reinforcement from the major reinforcement supplier in town 4 g8 ?7 ^0 c; W9 h
B.    the names of the major concrete suppliers in town $ t4 ?' }; |$ `5 r3 I5 E" u
C.    the dates on which the electrical trade closes down for the Christmas break
$ }) h5 @; M' w" j+ {D.    the date on which tenders are due for a large bridge construction project " Z- H% B& J$ n1 C1 {. o' B5 q  L

) u. d, v! h  f+ U* t58. Which of the following suggests an employment relationship rather than an independent contractor relationship? ( b" Z- k1 o* c$ Y; K* w
     
) b% U1 e0 {/ M( LA.    the person performing the work provides all of the tools and materials % i" g) K: {5 s1 U0 o6 E0 n- S+ m8 i( }  v
B.    the work is done when it suits the person performing the work 6 q7 A/ L$ |* A& q$ O$ N1 b
C.    the employer provides detailed instruction on how the work is to be done + R4 G) q/ y+ _3 j7 u% ^  _
D.    the rate for doing the work is negotiated for each portion of work
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:12 | 显示全部楼层
同言同羽 置业良晨
59. Zoe is a software engineer and is driving from her office to a client's office. Zoe's car is hit from behind by a polic car. Who can Zoe successfully sue?' J; L. T, E$ H; n. ]$ }4 E* Y

4 n# j/ l7 o0 e" t9 z( ?& `A. Her employer7 x& N0 v) W4 Z! C3 O
B. The police officer's employer* H8 K) m7 [( ?5 ?5 G+ j
C. The police officer4 S- h) @+ z" {3 K
D. None of the above
2 c, N2 v! k# Y" V9 Z( [& B
% v5 k9 V& _# e; K' e9 v60. Which of the following is true regarding occupational health and safety?
3 r& R/ z$ s- @/ [4 @1 ~+ m    : _0 m1 ?5 ?, z6 H
A.  in each province, there are many statutes governing occupational health and safety in different contexts   V# K" W3 i5 ~7 K" N3 J, h9 i' U
B.  federal legislation may set occupational health and safety standards in some contexts 0 G  @0 ]& _4 B3 N; f+ |9 M
C.  employers are required to ensure safe working conditions
, E7 U  _6 L2 h* l3 iD.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:36 | 显示全部楼层

下面提供考试真题部分答案:

见附件

1.doc

23.5 KB, 阅读权限: 2, 下载次数: 14

售价: 500 加币现金  [记录]

1-12 题答案

鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 20:55 | 显示全部楼层
61. In what circumstances might an environmental consultant not have to report the findings of their investigation to the regulatory authority?
" U% W1 k2 U3 n' }     
( h% h0 a9 n- }- U6 pA.  when the client, and not the regulatory authority, requested the investigation / c) m6 ]( L( g9 K# B; R3 j
B.  when there is a confidentiality agreement with the client
) X; O8 l8 e/ Q$ SC.  there are no such circumstances; reports must always be disclosed % n  A& b/ f8 v7 t  O
D.  when the investigation is requested by a lawyer for the purpose of providing legal advice and there is a comprehensively worded confidentiality agreement in the consulting contract
. t2 C5 M2 q6 U. u! Q6 ^
6 y9 L; l1 }/ I1 z  G6 h8 o% }62. Which of the following could be an environmental offence?
' v8 ^* H+ X4 G$ u     
4 B( U  H. j% e/ e2 @A.    failure to take reasonable steps to prevent contamination 1 p8 Y3 n1 ~. `* t; x5 t
B.    failure to keep accurate books and records
, T4 y& i" v- ~1 o$ D/ f* ]C.    failure to report contamination # U9 o$ d4 q& B* ^/ i7 L8 {
D.    all of the above
. `5 m4 V' K* b; A
- ]% x' Q7 l# Q8 W, X7 m+ M63. If a company causes contamination, who may be liable?
7 z% W  I9 e; N9 J2 ]* L( K+ W5 r
A. The company itself: J+ R  B: B9 _8 P
B. the directors
% N$ I( e- l4 `; o) G, X' v+ L8 O+ HC. the prvious landowner
) k0 E7 r4 k+ m8 _D. A and B
鲜花(64) 鸡蛋(0)
发表于 2008-12-25 21:19 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 22:07 | 显示全部楼层
64. Privacy legislation protects against the misuse of information about persons and organizations. Which of the following has the least protection under such legislation?
' P  _4 Z# W! \, T  C5 S( M4 h      
" e* ~' S, K6 Y# h# s4 u+ [A.    private citizens / T2 l6 J+ S! F7 D1 w1 I0 h. g; s
B.    partnerships * l5 O8 f; L# S# V: J1 D
C.    trade unions 2 |2 k9 j% j) m; D, M4 y
D.    corporations

Because corporations have limited liability.doc

23.5 KB, 阅读权限: 2, 下载次数: 11

售价: 100 加币现金  [记录]

原因分析

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 12:33 | 显示全部楼层

thanks.

同言同羽 置业良晨
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 13:40 | 显示全部楼层
同言同羽 置业良晨
65. What must a plaintiff prove in order to prove infringement of copyright on the Internet? 8 T/ J: T+ l- V# n
      0 \$ M+ o) h. H* r$ O$ c$ d" n
A.    that the work that was copied was protected by copyright ! I+ P- Q% ~9 X$ Z! y
B.    that the defendant actually copied the protected work , c9 _4 b8 Z5 z# _/ |
C.    that a substantial portion of the work was copied
0 w0 Z& Y/ u" g0 X" ^" dD.    all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:15 | 显示全部楼层
66. Which of the following is a correct statement of law?  2 H* `% ^1 ?% V+ i% C2 Y
     6 C5 M. `  H0 v
A.  standard form contracts always contain both general and special provisions # ]* s2 g$ M; G
B.  courts do not imply terms unless it is necessary to give effect to the intention of the parties 3 a5 v& j+ I% {/ A  k8 _1 ?
C.  where there is a conflict between general provisions and special provisions, the general provisions apply 6 U0 C* P5 X: H
D.  contracts cannot have supplemental conditions, all conditions must be included in one document
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:54 | 显示全部楼层

下面提供考试真题部分答案:

老杨团队,追求完美;客户至上,服务到位!
见附件

2.doc

26 KB, 阅读权限: 2, 下载次数: 7

售价: 1000 加币现金  [记录]

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 15:49 | 显示全部楼层

回复 85楼 的帖子

can't open these attachments, can you help out?
鲜花(0) 鸡蛋(0)
发表于 2008-12-27 08:56 | 显示全部楼层
啥时候办班?先报个名。
理袁律师事务所
鲜花(0) 鸡蛋(0)
发表于 2008-12-28 12:16 | 显示全部楼层

playball 你发的真当是好东西!

谢谢! 等着你继续发!
鲜花(0) 鸡蛋(0)
发表于 2008-12-29 12:22 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。+ p- P7 W# y6 |5 Z/ y8 B
Appega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。
& M4 |5 L! f; q. u0 W" @$ z0 ~- E+ l这些题目可以帮助学习,但不是考题。
9 D: g) A+ G9 k另外,透露考题是一种违反APEGGA的道德标准的行为。尤其是在道德考试前,每人都要签字的。
0 O( Q+ @$ I" j3 S5 _8 ?考试并不难, 只要下一定的功夫,都能通过。
$ M" S, D6 U' n. B- Z并且,通过学习,可以了解加拿大的道德观和法律(这是和中国有相当不同之处),会对每一位中国移民工程师有帮助的。
; Q, h6 d" L( X/ ^& I1 y4 N大家不要舍本逐末,为了考试而考试,忘了更重要的东西。
鲜花(31) 鸡蛋(0)
发表于 2008-12-30 09:57 | 显示全部楼层
原帖由 LAOZANG 于 2008-12-29 12:22 发表 " D! L5 y6 E9 a7 h3 }* {
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。3 Q0 l( W6 \8 N6 R( q9 q. D
Appega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。) o4 g7 m; o5 l) Z
这些题目可以帮助学习,但不 ...

$ U. A( S, f  {& o. w$ X, b& ^% j
您需要登录后才可以回帖 登录 | 注册

本版积分规则

联系我们|小黑屋|手机版|Archiver|埃德蒙顿中文网

GMT-7, 2026-4-23 14:33 , Processed in 0.323519 second(s), 27 queries , Gzip On, APC On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表