 鲜花( 1)  鸡蛋( 0)
|

楼主 |
发表于 2008-12-23 13:59
|
显示全部楼层
51. What is the key weakness of bar charts as a scheduling tool?
: q k. Y: M( v
# ~0 T8 b/ I+ g+ U- {A. they are hard to understand
0 m/ @6 C" p0 B3 B) W6 G) {B. they take a long time to produce . H; [: f% }, H) J# }, d% ~, I
C. they do not show an inter-relationship between activities
) x* A& z$ y1 L* m, P6 [D. it is often impractical to estimate the time a particular task will take
9 e% k$ L' F- r( x) ^3 ]% y
/ \: [" W. S, R0 }6 Z' I4 `0 u5 x5 o x52. Which of the following elements of a delay claim is generally the most difficult to prove?
- A1 a; s8 `3 F; b8 r- B2 `+ @ 9 L/ \( B) b( [* b$ w, C
A. the amount of additional cost caused by the delay, or acceleration
5 W7 E8 V, m9 |% ^1 U) `& a- ]B. duty to not interfere with the other party's performance of the contract 0 ^; U7 f5 U$ {3 q
C. breach of the duty to not interfere
1 G3 T2 m5 [, K! [D. that the breach of duty caused a delay, or a need for acceleration , R; g; p7 }$ R, n$ `4 e9 h
+ s7 }5 @) d" d R7 s5 k) Y5 x53. Which of the following statement is true in a standard CCDC2 contract?) c. N$ d, q9 _- x6 A* j+ a2 r
: J4 \7 T3 Y. a& }, Z
A. A compensable delay is not excusable
8 |% ] F! s. WB. A contractor-caused delay is compensable
+ l9 D/ U# b+ |- h( [3 sC. A contractor-caused delay is not excusable
" t8 i$ [' ~3 Q5 R* M* DD. Critical path activities are those in a sequence that must individually be completed before the next activity can begin. |
|