埃德蒙顿华人社区-Edmonton China

 找回密码
 注册
楼主: playball

[聊天灌水] 加拿大职业工程师考试--一起切磋

[复制链接]
鲜花(0) 鸡蛋(0)
发表于 2008-12-18 22:11 | 显示全部楼层

回复 60楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
能否将您这些题目的答案也公布一下?多谢
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 16:10 | 显示全部楼层
22. Under which of the following project delivery models does the contractor not have significant incentive to reduce costs?   K. e* o7 O$ E- t/ g

" K  H9 r( T% \0 K) c/ m/ K, \A.     alliance agreement
& f& p- h' |" j8 |3 A  _3 ~" [B.     cost-plus contract
  v) f! K0 N5 d$ d. OC.     fixed price contract
' Q: p$ C3 Y6 ?D.     unit price contract - R' q, s) |, E7 d1 d

2 B" J( I1 r3 L5 ?. w23. For which of the following types of contract would the scope of work clause be most detailed? . W; ~5 ^- F# A4 t1 L7 O
  
" S! A; F, y% c3 `" `A.    unit price
& G8 g7 G5 ?4 Y2 }) `& B% t* w+ p) oB.    fixed price for a design-bid-build project
3 v# [1 T' Y. W( _C.    fixed price for a design-build project
4 ?' F% S. s! k8 t' i( |D.    cost-plus
! f2 S1 ]4 A- f6 q; A# P, G4 H  P& w1 `
24. What is another name for an exclusion clause?
% x9 u+ ~3 ?3 J, [ . P% G2 \: c' b& S% t1 h
A.     escape clause 7 ~3 h, ~2 c8 {9 ?6 g
B.    exemption clause / c. l. H0 J7 ?  Y- k* @
C.    all of the above
* I: Z5 `9 M0 {" {( }D.    protective clause
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 17:54 | 显示全部楼层

声明

原帖由 Ape 于 2008-12-18 22:11 发表
3 l# t* o+ |8 M1 U0 a能否将您这些题目的答案也公布一下?多谢
( l* O+ D$ \: @$ d; b* k
& V* g. U4 _2 v# a
1. 本人发帖的目的是为了帮助大家通过NPPE考试, 旨在落实到行动, 把平凡的工作做精做细, 发扬光大下;
$ J7 g" [/ y+ C3 d
3 I' {. c3 @2 R9 S/ q2. 总共将有100道考试题目帖上来, 作为大家考前摸底; 如果你不能通过这套题目的话, 你还需要继续努力;; u2 u" I# y% f# V0 {. d
6 z9 F) A/ A5 w6 g8 t
3. 答案将在最后被帖上来, 供大家参考.
* Q" O5 x1 d! v& Y" d
  x. y+ P" U7 ~& A  v$ v4. 有的同志, 通过了考试拿到了证书的而又在网上大言不惭的, 也可以重新测试下你的水平, 达到从根本上消除你狂妄的口气.
鲜花(0) 鸡蛋(0)
发表于 2008-12-20 00:00 | 显示全部楼层

回复 63楼 的帖子

老杨团队 追求完美
非常感谢,将一直拜读下去,希望早点见到全部。不过上一次结束时是27题,这次怎么又从22题开始了?且内容同前面同题号的题不一样& u9 a$ W$ W* G2 D
3 O1 d3 ?7 G  Y. U! F8 o1 E" z
不要在意别人怎么说,其实通没通过差距不一定很大,可能就在一两分之间,很多刚考完的人出来说心里没底,只等通知了,有一定的运气成分。当然我们还是要好好准备才是。
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 17:47 | 显示全部楼层
对不起, 序号弄错了, 不能改正了. 接着来:2 F7 t% p0 Y% b* H% W% R# P
7 g" H1 k( l* w# p' ~( F
31. Strict liability can be defined as:
# f7 }3 b: e$ h/ I; w" ~  
, t3 L" \; q! C% {! t" K! EA.    liability flowing from negligence 5 ~7 `: t; f' B: f6 H* J& l$ ?
B.    liability for the fault of another 1 A* o# ?1 @2 n" u5 ]
C    liability without fault ! l$ R( j. Z) {3 j; t& D& |2 @7 j
D.    none of the above
8 I) w+ V$ N, y# C2 y1 \
4 R& q7 ^! k( J/ [32. Which of the following is pure economic loss? 1 \" {; t9 w& H' i* d8 X8 |: O( |

/ j# Z& t; j( [" t7 K; ?: dA.      the lost profit of a hotel after the power went out because a motorist knocked over a municipal power pole , K' @5 g4 o+ Z+ H7 Q( `0 m+ x1 R
B.      the painting repair cost after a roofing contractor carelessly chips the paint on the walls of the house
5 T$ p7 z8 A8 c/ y+ k5 H7 v& bC.      the repair costs after a cyclist's bike is damaged by a careless motorist
% G( x: ~) u. ^5 Y- ]1 K) I: H/ ~9 QD.      the medical costs associated with a car accident injury  
: T! o) h" _. ?9 P7 H: H
& |$ V& F0 P9 f1 V33. Which of the following may succeed as a defence to a negligence claim?
( U0 T3 g% o6 k' O8 j* }. @
2 }! V2 i/ G0 O/ D6 c% L5 E7 j+ dA.      the victim is an illegal immigrant $ F5 V$ \5 k- _5 S6 @3 J) P7 E# w
B.      the defendant met the standard of care required in the circumstances
# ~7 _+ D: ]" ?+ L/ mC.      the tortfeasor did not intend to cause harm to the victim
" q& N6 V5 L' @  SD.      the victim is far wealthier than the tortfeasor
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 23:09 | 显示全部楼层
34. A third party to a lawsuit may be added by 2 t9 R3 d0 a( K/ f/ j( \  ^8 M/ s+ |

2 T, n) w' f* @' d; B1 x$ R3 HA. either a plaintiff or a defendant( V% H6 S- I+ S) [6 D( q
B. plaintiff& y2 t- ?: j7 g+ y1 V9 u
C. defendant
' Z% s9 y# P& f7 [0 E4 ZD. none of above- z0 R5 s3 c% V* s( I
! ~# M$ t* |( p4 p  p0 S
35. Limitation periods are defined:
  x5 Y* M. V" ]5 ~" m- W3 P0 |" T3 E9 T$ _% x$ g
A.      by the courts as part of the common law + T! p( M- o7 I2 Z! V2 M( Z! j
B.      only by federal government legislation
- N: v. K* u% }! v( Q2 {9 yC.      only by provincial government legislation
  F, k& e' f# K* Y  ~. \( f" t7 hD.      by federal or provincial government legislation, depending on the subject matter of the limitation period
' v$ _3 Y  ~1 M! L9 c; A2 D$ w9 m$ I8 A3 k
36. If a plaintiff was 30 percent responsible for his or her own loss, damages will be reduced by 30 percent. What name is given to the doctrine that imposes this reduction?
7 g- B5 B! k: }" X# j     
) R: a9 n8 z+ z& CA.     joint liability 7 V! }, H" _5 t
B.     joint and several liability
! R8 b, A  Z7 ?; X5 B1 IC.     several liability 2 n! d0 `- H+ b  Y+ B3 L
D.     contributory negligence
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 14:31 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
37. which of the following is not a pleading?
5 e7 i  X& f, Y/ _+ }5 D! ~3 f8 I: X9 W, Y& v9 a8 T
A. A reply
1 o7 G6 ]2 d) A% kB. A statement of defence0 K2 u; v! g7 [! M
C. Discovery of documents4 J0 i7 D; x) g8 u8 v9 W
D. Interrogatories
7 l7 F  i2 B3 a* W- m5 v8 q
# |/ N% I+ }7 r8 ^( B38. What documents do judges examine prior to the commencement of a lawsuit?
0 G, e* x  o% o7 l/ x& G  w: C7 m3 j2 _- M/ [. e
A. The statement of claim
, v& L9 Y% G5 n. MB. correspondence between the parties' {( W' G' V1 A, \
C. photographs' t9 w& d0 _  q6 B+ M
D. settlement offers" ^" n' a6 J* _" N, `  n2 e
$ u/ E5 \7 k6 m+ I; x, s7 N+ Y' J
39. Which is generally the least voluntary method of dispute resolution? 9 Z, v# n, Y% {3 b8 |1 i" s
     
9 g$ F0 K: Y8 `& K( s) C7 jA.  litigation
& Y& |) \, h+ X+ q9 O- F0 _) {1 U8 VB.  negotiation
9 d3 x1 S: W" O, ~0 AC.  mediation
9 L3 |* V0 M+ w6 ~5 Y" _4 }' bD.  arbitration + u4 d/ F" G% g% r( g- s) j! F

# v  e% U' W% {8 x4 A" @+ q40. Which of the following methods of dispute resolution offers the advantage of privacy? - M7 U, O7 v0 Q2 @9 n7 j
     
& b( t7 n2 c- X* x/ K2 LA.  arbitration
5 w& K/ h+ Y0 vB.  mediation % w$ @; {1 `" n6 O$ A+ N8 Y' r3 o
C.  negotiation ) M6 z* ]) E5 W6 p
D.  all of the above
理袁律师事务所
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 21:05 | 显示全部楼层
41. Which of the following may require further design work by the consultant relatively late in the project? # ~2 O- Y  j' w8 |
    3 S9 I1 }1 b- t+ Y2 Z
A.  contractor error 9 G" O8 s3 G6 P
B.  tenant requests
5 E  `! l" b& xC.  unforeseen conditions : y2 J. V2 q9 D1 O
D.   all of the above ; `. P5 g/ B5 ]% O. \5 p8 W0 @

& O2 j  {, K9 h7 U2 {; O42. which of the following is not a contractual risk allocation provision?
7 z* G% A# ]& a( j' P9 l7 s- k4 E
( a4 @5 C2 S) j4 P6 |A. An insurance clause
; n, g" V, t- Y: _: l9 J5 ~B. An 'unforeseen conditions' clause/ s0 ^- O* l* O( E
C. A pay-when-paid clause5 d2 M8 I, f4 x( h' X
D. none of the above
鲜花(0) 鸡蛋(0)
发表于 2008-12-21 23:33 | 显示全部楼层

回复 68楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
感谢。
' S0 Q5 n) D- g这些是以前考过的真题吗?
3 {; A# X5 m, K2 q; R1 U( b0 c* e  |+ z请继续
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 11:18 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
43. Which of the following may result in loss of insurance coverage?
; ^, s  ^2 Q- ~0 j
$ D7 v' ^5 i$ j  SA.      failure to comply with the notice provisions
. \2 e! p+ u" G0 M/ O' @; }6 g7 jB.      lack of insurable interest - w& J; g. g$ y9 X
C.       all of the above # z6 i4 J4 b& m  ]
D.       material non-disclosure
/ O0 N2 D5 e. I1 |; n3 A* W. h" u% e* \
44. Which of the following is true?
3 p% d1 g2 ^0 ^. a% B1 {; W. W& B# Q1 p% e
A.      professional liability policies are normally claims-made policies ' M, p; A2 s  ]/ o
B.      a claims-made policy covers liability for events that occurred in a specific time period  9 p% h, L' I- P5 ~* a1 C, w
C.      property insurance policies are either claims-made or occurrence policies % R, ]# e5 V3 p% ?. c0 e' S. ~7 f$ u( U
D.      none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 14:11 | 显示全部楼层
45. which statement is true in the following:
$ [, [$ U7 D' e
. a) Q3 K6 g( t$ `- W) wA. Sub-subcontractor qualify as a claimant under a standard form CCDC labour and material payment bond;
9 G* ]( G/ ]0 s* ?0 `B. The limitation periods available to the contractor may not be available to the surety;
+ O1 s8 W; U* C* vC. The limitation periods available to the surety may not be available to the principal;& e1 ~6 t6 d6 Y/ q5 l; x
D. labour and material payment bond is not a one-tier bond.9 [8 c0 R+ m$ N

& W* S2 ?- j( M* Q( R1 C, e' R2 u46. Who may be an obligee under a bonding contract? 3 g' D' q( E& ?. L# s
      
, U& t& |1 U* o) t1 m  L& \9 S1 ^A.  the general contractor 8 t) B, w$ h) e! ?
B.  a private owner
. J$ u+ }' |' m( ]' n* GC.  the government
. L# u* {& m+ i/ {' O. f2 Y! cD.  all of the above
  M: ~$ w3 \: B& s5 u* x: m" i3 [* e! E# m# }  o) f1 I
47. A bidder bid $80 and then refused to enter into a contract with the owner. The other three bidders bid $88, $90, and $100. The owner accepted the $90 bid. The face value of the bid bond was $9. How much is the surety required to pay the owner?  
1 c5 U+ z* o+ @   
) O5 r" K4 W$ R* FA.  $20 3 |" d* G) U; S3 R/ @# y7 y9 D
B.   $9
: a9 E' f" c4 N& BC.   $8 ' j/ f1 Q4 X" V; F( ], c( x
D.   $10
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 09:58 | 显示全部楼层
48. Which parties may be potentially liable for a breach of trust under a Construction Lien Act?
" i$ Y& o  b2 }/ O$ _6 }6 E* _6 Z* i% a# h% U! M
A. Owner9 g& G6 z9 m/ l3 d2 L1 _. B
B. contractor
" S$ Z( {0 ^' }0 s  [C. worker9 H/ w1 p+ m. d7 a" O( j; M
D. material supplier
* G4 U: b, @5 M2 c1 B* v5 u6 u% h8 c8 ]: _) m& t; V" y* u3 _
49. Against what property does the lien holder have a cause of action?
7 @6 R( ]! u" r* I5 T  e' y: L      ! N3 `! f& ~( j1 z% @4 B' Q- ~7 g
A.    the interest that the party the lien holder contracted with has in the property on which the work was done
% b7 R/ Z7 A0 _4 FB.    the property owned by the party the lien holder contracted with
9 S& W6 O, [6 `C.    the property on which the work was done
5 K  }: G: Y' l; e6 d8 B7 K% yD.    none of the above 3 Y/ S/ b! `+ k0 c* p
" D7 L6 J9 E* X% s& ~( Q
50. An owner providing substitute security for a lien is, in effect:  8 z& Q) l% e4 X1 l" s
     
" U. W- A9 I/ K3 b" Q2 NA.  reducing his chances of having to pay out on the lien
; q% |0 n6 d0 w4 H$ H5 LB.  not changing the likelihood of having to pay the lien amount 4 k+ [3 P+ c/ `+ e" y5 ?% b
C.  admitting liability for the lien ( ?0 n8 O3 i) S  b* `
D.  none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 13:59 | 显示全部楼层
同言同羽 置业良晨
51. What is the key weakness of bar charts as a scheduling tool?
& ^6 C5 ?! H4 V5 p  M1 T6 L      2 t: r1 w  h" y8 t. _  L
A.  they are hard to understand
; _9 y" g: J, PB.  they take a long time to produce 1 }0 C8 H( z' z% U5 S
C.  they do not show an inter-relationship between activities
0 X& @) W& |1 S/ oD.  it is often impractical to estimate the time a particular task will take 0 ?8 o- ]0 I# p7 [; H7 a
2 }  ~% m* d4 x- U, c
52. Which of the following elements of a delay claim is generally the most difficult to prove? - ^4 p1 f0 p: N' c( O6 D2 T
      
- O; x8 M0 J, l! k: x+ B1 aA.  the amount of additional cost caused by the delay, or acceleration ) o7 h- v" N, ~! M9 p
B.  duty to not interfere with the other party's performance of the contract
( J4 y# R0 W9 k  @6 P' `C.  breach of the duty to not interfere ( {: `, K! L( c
D.  that the breach of duty caused a delay, or a need for acceleration " ?: ?, }" a+ @& Z5 L/ i
! m- C4 Y( }9 W: J! d& b
53. Which of the following statement is true in a standard CCDC2 contract?' t+ S3 `$ U( W- \5 @9 z

/ d, q! L" T1 BA. A compensable delay is not excusable/ q/ z, C: u. Z1 \2 k0 c4 }
B. A contractor-caused delay is compensable1 I3 c: W$ g5 @+ Z/ d6 U
C. A contractor-caused delay is not excusable
; u$ Q" j' f2 U; E5 mD. Critical path activities are those in a sequence that must individually be completed before the next activity can begin.
鲜花(0) 鸡蛋(0)
发表于 2008-12-23 21:13 | 显示全部楼层

回复 73楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
good job. a lot of questions for practice laws.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-24 22:35 | 显示全部楼层
54. Which of the following is not true regarding an employer-dependent contractor relationship? 9 i4 M+ F& G( n
      5 ~) e  z: X' b
A.  the contractor may use his or her own tools 0 r! |/ b- w! |" Q8 O; m
B.  the contractor is generally not trained by the employer
; a% @3 J- C6 m; {5 {' F7 `C.  the contractor will generally set his or her own work hours
: ^, d8 X( q) [0 WD.  the contractor is generally economically independent from the employer
( P. z9 v% t, A9 @0 i9 g) y$ O6 e  o1 M0 N. J
55. What term describes the situation in which workers are required to pay union dues but not compelled to join the union?
% N: {) E2 v* ?+ K, o     , \$ ^: a/ m" A
A. rand formula 0 ^$ m, b; |, e, I  i0 ]6 D
B. union shop
: F$ V( n. D4 S" y( u1 U8 KC. closed shop 6 M+ a' G; `( R
D. open shop
: H& D% u$ E/ g+ |5 U * l7 s9 g4 k" [9 s  G$ v
56. Which statement is true of an employer under a typical collective agreement?
6 K' D$ P8 z+ A  t/ h) S- w0 [4 I- p! ]# P" m1 g* S! A; G% c: s3 h( v6 ]
A. The employer cannot terminate an employee under any circumstances;% ?9 y$ D: U# _7 J  _
B. The employer can only terminate an employee if he gives reasonable notice;+ Z! X: X( V6 ?3 W) x3 y3 W
C. The employer can not lay off an employee because of a downturn in business;. @& D2 r. ]- w, o0 B+ c; q* u% w
D. none of the above.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 12:10 | 显示全部楼层
57. Which of the following would likely be confidential information of a contractor, which a construction manager going to a new job should not share with his or her new employer? ) M1 z+ k$ H0 c) r; U; p
     
- ~9 k: ?$ Q3 X2 D1 a% l1 l% h. }A.    the price the contractor pays for reinforcement from the major reinforcement supplier in town
3 s0 v3 j: l& u3 i0 vB.    the names of the major concrete suppliers in town
5 c: N' u0 U6 P* l) K. |C.    the dates on which the electrical trade closes down for the Christmas break
! {1 C0 x$ C- eD.    the date on which tenders are due for a large bridge construction project 7 [1 n: c2 q1 u% l  Z! {3 d

) c9 }7 p5 {! P58. Which of the following suggests an employment relationship rather than an independent contractor relationship?
, N, f- W. ]1 M' L9 i     
9 h4 V, e; c1 p& HA.    the person performing the work provides all of the tools and materials
- z- y4 p$ U+ a( G- ]3 a. {B.    the work is done when it suits the person performing the work
5 ]/ C% E# ~" \7 tC.    the employer provides detailed instruction on how the work is to be done
3 T4 C8 x2 n' n1 b8 w: I- lD.    the rate for doing the work is negotiated for each portion of work
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:12 | 显示全部楼层
同言同羽 置业良晨
59. Zoe is a software engineer and is driving from her office to a client's office. Zoe's car is hit from behind by a polic car. Who can Zoe successfully sue?
, ?/ B- _' t  @6 \/ I5 S. N" {
8 K3 D( V0 e+ jA. Her employer
2 d6 x1 j! r$ G- P% Q) ]! x5 lB. The police officer's employer
+ {( q* A& @3 r& ]+ R/ ?2 tC. The police officer
7 L8 R  j, L) \D. None of the above
, V8 |  q6 j9 a8 ?# ]4 w6 n3 G# H# p8 K. B, ?- x
60. Which of the following is true regarding occupational health and safety? 5 g; i! b7 |8 g9 m
   
7 K' d( ~1 E) ^% o' e3 n& {. DA.  in each province, there are many statutes governing occupational health and safety in different contexts
% m  f' n+ V  gB.  federal legislation may set occupational health and safety standards in some contexts * E4 x0 p9 k8 E1 b# ~1 c
C.  employers are required to ensure safe working conditions
6 n! }# K% S9 G# V4 I9 c( DD.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:36 | 显示全部楼层

下面提供考试真题部分答案:

见附件

1.doc

23.5 KB, 阅读权限: 2, 下载次数: 14

售价: 500 加币现金  [记录]

1-12 题答案

鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 20:55 | 显示全部楼层
61. In what circumstances might an environmental consultant not have to report the findings of their investigation to the regulatory authority? : Z) Z* }0 L9 R! M8 `' ?
     
) n. J0 N7 k4 z$ KA.  when the client, and not the regulatory authority, requested the investigation ; y) g7 {1 W/ s. w! s  y4 F7 }' x3 }
B.  when there is a confidentiality agreement with the client . W* o: W  M6 @
C.  there are no such circumstances; reports must always be disclosed
+ f7 W8 H0 g( y. R- q4 GD.  when the investigation is requested by a lawyer for the purpose of providing legal advice and there is a comprehensively worded confidentiality agreement in the consulting contract 3 G6 }" o6 y6 S9 [  M1 ~" p# I

& \7 J1 R: l8 T8 b62. Which of the following could be an environmental offence?
% o! L5 n. U' S' q" C' a; ]3 I     4 K0 R4 ]  w; d$ F
A.    failure to take reasonable steps to prevent contamination
8 v! }7 [8 R" Y8 p# PB.    failure to keep accurate books and records
5 R, ]2 n* z/ B9 ^C.    failure to report contamination
7 i+ j, o7 W1 e0 V9 @2 xD.    all of the above * J' N+ y. I: l0 N8 |$ H# G7 m" L. m
* w7 S# S' `. H/ |/ l: o2 q
63. If a company causes contamination, who may be liable?, }! f8 n/ S# X

  v" v5 F2 @( H: i* u$ k+ b6 aA. The company itself
9 _& ^- s5 e) J: oB. the directors
! e3 h8 s0 M: {. NC. the prvious landowner
3 O2 s6 Z$ r, F, Z7 U8 U/ YD. A and B
鲜花(64) 鸡蛋(0)
发表于 2008-12-25 21:19 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
大型搬家
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 22:07 | 显示全部楼层
64. Privacy legislation protects against the misuse of information about persons and organizations. Which of the following has the least protection under such legislation? % i; H) R0 l& f; D9 g* T
      
, h9 F4 H; r! BA.    private citizens
1 _7 y' K, F, U( aB.    partnerships
  j5 O# Y* F2 a/ zC.    trade unions
$ [& B: B. {& WD.    corporations

Because corporations have limited liability.doc

23.5 KB, 阅读权限: 2, 下载次数: 11

售价: 100 加币现金  [记录]

原因分析

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 12:33 | 显示全部楼层

thanks.

同言同羽 置业良晨
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 13:40 | 显示全部楼层
同言同羽 置业良晨
65. What must a plaintiff prove in order to prove infringement of copyright on the Internet? 2 L- O1 t6 |6 ~5 i, Y8 s
      
: w# v: R# y. O  F, _. \A.    that the work that was copied was protected by copyright 5 ]) q  M7 y* F) K/ k
B.    that the defendant actually copied the protected work
8 V0 `' B6 @6 f6 g: z) n- l7 `/ s7 BC.    that a substantial portion of the work was copied / {. ^& b% R/ A! ?) }( t2 E
D.    all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:15 | 显示全部楼层
66. Which of the following is a correct statement of law?  9 v  ?' r$ i/ V8 b+ _+ u, _( c
     6 G! h$ ?. o. q
A.  standard form contracts always contain both general and special provisions
0 i& i1 `! L  G: L6 u' tB.  courts do not imply terms unless it is necessary to give effect to the intention of the parties / |$ @, k% R5 E3 L( |
C.  where there is a conflict between general provisions and special provisions, the general provisions apply 8 N; ~& w' r: X# s# ]  |
D.  contracts cannot have supplemental conditions, all conditions must be included in one document
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:54 | 显示全部楼层

下面提供考试真题部分答案:

老杨团队,追求完美;客户至上,服务到位!
见附件

2.doc

26 KB, 阅读权限: 2, 下载次数: 7

售价: 1000 加币现金  [记录]

理袁律师事务所
鲜花(0) 鸡蛋(0)
发表于 2008-12-26 15:49 | 显示全部楼层

回复 85楼 的帖子

can't open these attachments, can you help out?
鲜花(0) 鸡蛋(0)
发表于 2008-12-27 08:56 | 显示全部楼层
啥时候办班?先报个名。
鲜花(0) 鸡蛋(0)
发表于 2008-12-28 12:16 | 显示全部楼层

playball 你发的真当是好东西!

谢谢! 等着你继续发!
鲜花(0) 鸡蛋(0)
发表于 2008-12-29 12:22 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。
8 ~: m5 L& u# `8 l; _( ?# jAppega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。9 x3 a/ Q1 z' f) r8 T: I
这些题目可以帮助学习,但不是考题。( Z# N8 P: b: b/ J8 O5 K* w/ J- |* F
另外,透露考题是一种违反APEGGA的道德标准的行为。尤其是在道德考试前,每人都要签字的。
- L' k  W& ^; e1 O) e考试并不难, 只要下一定的功夫,都能通过。
6 B' @- q; S3 N并且,通过学习,可以了解加拿大的道德观和法律(这是和中国有相当不同之处),会对每一位中国移民工程师有帮助的。
" i- y  N  L" t, Q# `. k大家不要舍本逐末,为了考试而考试,忘了更重要的东西。
鲜花(31) 鸡蛋(0)
发表于 2008-12-30 09:57 | 显示全部楼层
原帖由 LAOZANG 于 2008-12-29 12:22 发表 - M! j6 h$ L" x( S# w* L2 k
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。
. P: d0 p1 G: b5 B0 P: e! O& fAppega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。
% ^' ~. d# y' o3 L" o. I这些题目可以帮助学习,但不 ...

% S2 s3 C% p% S/ A9 p' y
您需要登录后才可以回帖 登录 | 注册

本版积分规则

联系我们|小黑屋|手机版|Archiver|埃德蒙顿中文网

GMT-7, 2026-3-28 14:58 , Processed in 0.171194 second(s), 28 queries , Gzip On, APC On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表