埃德蒙顿华人社区-Edmonton China

 找回密码
 注册
楼主: playball

[聊天灌水] 加拿大职业工程师考试--一起切磋

[复制链接]
鲜花(0) 鸡蛋(0)
发表于 2008-12-18 22:11 | 显示全部楼层

回复 60楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
能否将您这些题目的答案也公布一下?多谢
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 16:10 | 显示全部楼层
22. Under which of the following project delivery models does the contractor not have significant incentive to reduce costs? ) h; I. E5 i8 m5 l# G2 c' l5 @8 N
. [* w& F. |' U: j  }
A.     alliance agreement
$ W1 J1 t) I2 xB.     cost-plus contract
2 J; ?, O9 k8 fC.     fixed price contract : g# w9 K/ V5 }9 a
D.     unit price contract
' N) Y: a7 R  T3 w& D' w/ x
. v! P- I8 k. C- S! T* e6 m23. For which of the following types of contract would the scope of work clause be most detailed? ; n' l& ]  R2 F3 [5 u) f3 J
  8 I1 l$ n, P7 o# _. l5 J$ R
A.    unit price
  T0 S, Q6 ?1 P) v$ y$ u1 r. r. C! wB.    fixed price for a design-bid-build project
; q- s, h9 t- wC.    fixed price for a design-build project
" E  H9 {+ k+ s  t( tD.    cost-plus
& i) ?0 \& N! F$ a0 d$ S0 j
; }) E  c- c$ u. E$ }: C24. What is another name for an exclusion clause?
) O6 E* m, T6 j - A9 O: {% [+ i$ B, u
A.     escape clause
! h9 l. m7 ^6 m$ H$ I5 SB.    exemption clause $ Q2 @1 G1 [3 u4 D- h
C.    all of the above " b3 M0 t* Y7 C
D.    protective clause
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 17:54 | 显示全部楼层

声明

原帖由 Ape 于 2008-12-18 22:11 发表
* \& s  Y. i- S能否将您这些题目的答案也公布一下?多谢
% t% v) `+ K; N5 _1 |* l
7 U. z& n' |) P
1. 本人发帖的目的是为了帮助大家通过NPPE考试, 旨在落实到行动, 把平凡的工作做精做细, 发扬光大下;
5 `- C8 x, W7 h! m' z
  ~7 U2 I# a9 J2. 总共将有100道考试题目帖上来, 作为大家考前摸底; 如果你不能通过这套题目的话, 你还需要继续努力;
) d2 Y* A7 u& D$ G; X6 {4 C6 k5 N! A; N; ~! W5 \3 x6 a8 t6 ^
3. 答案将在最后被帖上来, 供大家参考.# ]* L2 X% X. M  g
+ y! b7 K  x) j/ j& S
4. 有的同志, 通过了考试拿到了证书的而又在网上大言不惭的, 也可以重新测试下你的水平, 达到从根本上消除你狂妄的口气.
鲜花(0) 鸡蛋(0)
发表于 2008-12-20 00:00 | 显示全部楼层

回复 63楼 的帖子

老杨团队 追求完美
非常感谢,将一直拜读下去,希望早点见到全部。不过上一次结束时是27题,这次怎么又从22题开始了?且内容同前面同题号的题不一样
" ~$ `/ O7 d) ]" W8 O! S3 I, U. S  X1 e! M
不要在意别人怎么说,其实通没通过差距不一定很大,可能就在一两分之间,很多刚考完的人出来说心里没底,只等通知了,有一定的运气成分。当然我们还是要好好准备才是。
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 17:47 | 显示全部楼层
对不起, 序号弄错了, 不能改正了. 接着来:
* @7 J: b8 ^! o% V7 y
7 S, l& i* U- Y" b, s! {+ y( Q& d6 W31. Strict liability can be defined as:
1 n$ ^* G+ ~) p! a6 l6 t/ f: K+ A" \4 M  
3 W; U7 L; N% k( d/ n, ~A.    liability flowing from negligence 9 V! k0 U/ p6 L# A
B.    liability for the fault of another 9 i3 q7 [* d4 r9 A3 K
C    liability without fault 5 e# y" Y$ O2 W7 l: |
D.    none of the above
) N& P" J0 `3 |1 d! Z5 Q& L. F# y! ]9 {5 D& S! {
32. Which of the following is pure economic loss? . G5 f7 Z. j+ [6 p0 p( `8 Y
6 P' \5 @& D  u4 K
A.      the lost profit of a hotel after the power went out because a motorist knocked over a municipal power pole & O$ t# q0 j1 V  g9 }
B.      the painting repair cost after a roofing contractor carelessly chips the paint on the walls of the house
: |; ^7 K# ~$ Z0 c2 I. wC.      the repair costs after a cyclist's bike is damaged by a careless motorist 9 J( J4 l+ A; s0 l* Y  W
D.      the medical costs associated with a car accident injury  
$ p0 J# ]3 s- v( G$ M/ a# d! a
: [4 `  o! W% c. _: ]33. Which of the following may succeed as a defence to a negligence claim? 6 v4 U9 P+ `+ u& r
# F2 R, R3 x1 N% X
A.      the victim is an illegal immigrant
! U9 W+ o3 [1 C# ^B.      the defendant met the standard of care required in the circumstances
' _! n4 g" C- a6 B) l' M% ~C.      the tortfeasor did not intend to cause harm to the victim - N- ~4 J  ~  ^5 W
D.      the victim is far wealthier than the tortfeasor
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 23:09 | 显示全部楼层
34. A third party to a lawsuit may be added by ) |/ [8 N/ q) w: ?. N  }$ e
1 E: w! f/ s2 l, j: O1 z. B% ^
A. either a plaintiff or a defendant. q& d) X9 m  t
B. plaintiff
7 b6 v! _0 C0 R! T& {7 t6 i0 ZC. defendant
  n  i2 w9 r7 P5 o1 sD. none of above
+ r! `* e" p( O2 M0 ]  R
& Z. g0 O. R. J( P, a& z  ?: \$ v35. Limitation periods are defined:
8 d+ [; {$ X: [% w& C' ]  M, j0 `" r  X
A.      by the courts as part of the common law   E  h* w/ b- H, @
B.      only by federal government legislation " X2 x' b8 |4 n4 t% E
C.      only by provincial government legislation
  a' W7 T5 s+ l1 wD.      by federal or provincial government legislation, depending on the subject matter of the limitation period 4 l- e+ P5 E, \: _' E, p2 ^

" a- B: Q! ?2 L+ X36. If a plaintiff was 30 percent responsible for his or her own loss, damages will be reduced by 30 percent. What name is given to the doctrine that imposes this reduction?
7 |* K0 l/ v* `; j     
% q% B/ C6 ?  S: tA.     joint liability
3 M' L- }) _/ Y, H: B0 [B.     joint and several liability
' l7 B1 G% k& ?2 m6 M7 mC.     several liability
9 k. s6 Q8 ]) X& U* f; u0 l0 ?D.     contributory negligence
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 14:31 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
37. which of the following is not a pleading?) w& r: ~* L& c2 f! I3 f  M: O

, j9 \$ N$ d! o; o9 cA. A reply
9 R1 s! ?! I# C2 E! X3 ZB. A statement of defence" x, R# v5 n: m3 @( g
C. Discovery of documents* F0 f- N/ F; f+ s. G0 \) b! E
D. Interrogatories# J: O5 p* A3 B! {* O$ b
* L$ I' ]* H5 Z4 z
38. What documents do judges examine prior to the commencement of a lawsuit?
3 h1 c8 w: ~1 o2 ?, n& o7 @% E3 r$ M' v; W" L6 Z' E8 ^
A. The statement of claim
1 q* p* R! s+ ]% z3 }) dB. correspondence between the parties
) {5 s, B. C! ^8 h8 Y; I; o3 c/ d9 `, FC. photographs8 G% R4 S; c) V! @) i" J
D. settlement offers% V) J2 ?: ?9 I

/ l, m, s2 P. a, A) O39. Which is generally the least voluntary method of dispute resolution? 2 y# s; q) D! C0 P+ a4 A2 B+ L; M4 d
     
2 f8 S. J! O  s0 j, W% \A.  litigation
3 d  H! C/ v' J) E" pB.  negotiation % T# Y4 ~0 {" z6 l! W$ |$ X7 N
C.  mediation ( @- z: Y$ K) F: T  `& m8 H3 j' E4 f
D.  arbitration
4 ^5 c+ b) b7 c. z+ D7 x2 L+ @& x" f  i. b
40. Which of the following methods of dispute resolution offers the advantage of privacy?
* n! n( Q! S$ D$ ?0 k     ; _, B8 m. G! s) I$ q
A.  arbitration * f4 J5 N+ z; O5 S* t2 h
B.  mediation
( E/ N/ C$ b% |5 W0 e2 mC.  negotiation " F' T5 [' A& v
D.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 21:05 | 显示全部楼层
41. Which of the following may require further design work by the consultant relatively late in the project? 3 O# W% L; G8 E" A9 I
   
- P8 _5 K- a2 q) I9 MA.  contractor error : f1 `; P/ H% V  E7 t* y. {
B.  tenant requests / g7 u5 {3 u$ y7 r! P9 L$ i% I
C.  unforeseen conditions
) w5 @) t! F, E- aD.   all of the above 3 r6 D) Y  f" j6 W$ o

$ \1 r+ Z& l7 N0 d2 P; ]0 ?42. which of the following is not a contractual risk allocation provision?
( B- E4 D" R9 ?$ A( \, s/ l
: q& F( Y5 M) G* ~( P. g( GA. An insurance clause8 P6 O( F* c2 s/ p% v& c) d5 A' Q
B. An 'unforeseen conditions' clause/ T7 m( H! T( _" L6 P
C. A pay-when-paid clause
: \3 p3 M% ^. P/ e6 a/ y  pD. none of the above
鲜花(0) 鸡蛋(0)
发表于 2008-12-21 23:33 | 显示全部楼层

回复 68楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
感谢。
4 ]4 R/ _( c3 `" }5 I+ f8 p5 x1 u: x! G这些是以前考过的真题吗?: Y4 f# ^4 R# d8 E! ~2 k; k
请继续
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 11:18 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
43. Which of the following may result in loss of insurance coverage? & z8 \3 x6 a, v0 x% f
0 I, p/ w" {: F. V: J. b+ {
A.      failure to comply with the notice provisions + g* i3 {1 ~: z" C
B.      lack of insurable interest ! V1 U( S  h! K  V2 h( z3 ^
C.       all of the above ; |8 ^7 {/ P% o# m6 S! F9 P, S# v
D.       material non-disclosure + e& q+ g2 b& v3 B! R
0 \8 a# e" v% \$ p) W
44. Which of the following is true? ; r& L6 ]. t0 L" b
  V9 R4 b0 P9 g: D
A.      professional liability policies are normally claims-made policies
! z: e# G/ I2 `4 P: E0 MB.      a claims-made policy covers liability for events that occurred in a specific time period  5 I! J  [. l1 x; w7 A
C.      property insurance policies are either claims-made or occurrence policies
: |! c. F+ E% GD.      none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 14:11 | 显示全部楼层
45. which statement is true in the following:* x( l9 Z8 c: [+ W7 ^" X; R
: d$ z+ u: s, h7 Z, X8 h
A. Sub-subcontractor qualify as a claimant under a standard form CCDC labour and material payment bond;
8 z* K+ r, b+ A) WB. The limitation periods available to the contractor may not be available to the surety;
* J  k! V7 l! \. e" c/ D- sC. The limitation periods available to the surety may not be available to the principal;1 D% M5 \7 |, @+ V
D. labour and material payment bond is not a one-tier bond.
) x+ X) o. ]) q2 I+ S9 Z. F8 h5 m  C" c, d% a# X+ `" l( r4 |" X' P
46. Who may be an obligee under a bonding contract?
' A/ K( Z% ?1 W, D, f$ J      
  T; _; E$ o6 |3 I8 @* ]1 ?- ?A.  the general contractor
5 p" F. c1 D; @) N& DB.  a private owner
3 A7 i7 @$ O8 w! r8 G' I5 AC.  the government
- z, y$ I( n; q. \3 B; dD.  all of the above
- x, ~/ E9 l6 E6 M% M7 a. s
- {" e2 b7 G* g6 K# ^3 Y6 Q; }5 g47. A bidder bid $80 and then refused to enter into a contract with the owner. The other three bidders bid $88, $90, and $100. The owner accepted the $90 bid. The face value of the bid bond was $9. How much is the surety required to pay the owner?  5 l+ `! {; ^9 |) Q" ]; e3 m. A$ b
    7 c0 B/ V0 ], z8 b# |7 w
A.  $20 7 i9 B# j; ]& B! \2 u; p1 G3 g) R
B.   $9
+ F3 V1 B! m. P8 Z& A0 q9 MC.   $8
& j. N% W; D, O5 a3 R+ c. ID.   $10
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 09:58 | 显示全部楼层
48. Which parties may be potentially liable for a breach of trust under a Construction Lien Act?" u# o9 e2 c- d9 c$ K1 ?
, _( u$ ], Z: q# {$ a
A. Owner
7 `% J* W1 Y  l& }% RB. contractor& e7 M/ |( b" h: i( u* f3 ~
C. worker
7 k; d  ~5 L- n* d6 U7 U: q! MD. material supplier# x9 K. m: T/ O- V* H" ^
* q; X' z/ ^0 p# a: T
49. Against what property does the lien holder have a cause of action?
3 U  h+ s1 |5 C. T& m      ' c& h  M' l, }$ g1 @
A.    the interest that the party the lien holder contracted with has in the property on which the work was done ) `! w2 T; j! X; M4 D
B.    the property owned by the party the lien holder contracted with
) n3 n4 \$ t4 {9 EC.    the property on which the work was done   E: ]2 f8 R6 ]
D.    none of the above ( ^- C: T0 c: ^2 }; g& f6 V

& b2 |- ^' u: s' U" ]+ w; [50. An owner providing substitute security for a lien is, in effect:  8 }. W: {! G7 t$ ]8 V
     
9 G/ |! ]- l! z0 @  \A.  reducing his chances of having to pay out on the lien 0 A/ L5 p" q5 t+ t$ e% P) y, E
B.  not changing the likelihood of having to pay the lien amount + T: J. v- A; i2 ?/ J
C.  admitting liability for the lien
6 K1 U+ u, ]( k% ?" gD.  none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 13:59 | 显示全部楼层
同言同羽 置业良晨
51. What is the key weakness of bar charts as a scheduling tool?
" V/ k# X4 I3 ?: T9 N* a      & W. i1 v, n+ r5 j/ c, ~2 I7 l
A.  they are hard to understand 5 g& n% W+ B" L( o3 z6 [
B.  they take a long time to produce - H: w* B9 C& z3 i# `
C.  they do not show an inter-relationship between activities , |( f8 P' J8 F- E5 A: F9 [
D.  it is often impractical to estimate the time a particular task will take % t4 @  ?  ^5 S, \7 T7 J3 G
+ `. Q4 g! B6 \3 s: {
52. Which of the following elements of a delay claim is generally the most difficult to prove? - k0 x! q8 o$ k. j8 w
      
( e0 s9 @9 @+ d$ t& EA.  the amount of additional cost caused by the delay, or acceleration
2 n% A4 D3 x7 i, LB.  duty to not interfere with the other party's performance of the contract
4 ~1 q2 B- h8 ~# H7 oC.  breach of the duty to not interfere
1 y) k: j: X. [8 @! Y* `! dD.  that the breach of duty caused a delay, or a need for acceleration 4 w: U9 b5 [) x- K/ [
, K, i3 u7 C  F; }2 {$ `: i
53. Which of the following statement is true in a standard CCDC2 contract?! ~& S; T2 O' z/ A/ t; J3 n

* `" B6 v/ X" L2 x, w% _8 cA. A compensable delay is not excusable$ J$ g$ m) w; G. B1 V0 g
B. A contractor-caused delay is compensable
$ t( ~: }/ `4 E7 ^2 sC. A contractor-caused delay is not excusable$ y* ~8 `- g& G
D. Critical path activities are those in a sequence that must individually be completed before the next activity can begin.
鲜花(0) 鸡蛋(0)
发表于 2008-12-23 21:13 | 显示全部楼层

回复 73楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
good job. a lot of questions for practice laws.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-24 22:35 | 显示全部楼层
54. Which of the following is not true regarding an employer-dependent contractor relationship?
7 f% x2 o  w6 H/ u  g      
5 `9 h( o4 N( rA.  the contractor may use his or her own tools
' _" d8 \) u5 O, ^% f' |3 sB.  the contractor is generally not trained by the employer ; s3 x  v4 j0 W! }
C.  the contractor will generally set his or her own work hours / g3 V( q" R1 ?; J! f
D.  the contractor is generally economically independent from the employer ( E7 y) u+ _- y! y
: I. l5 T, o4 p" a9 J/ ~& T: Y
55. What term describes the situation in which workers are required to pay union dues but not compelled to join the union? 4 e% V1 o6 _0 j- k9 p) w! V* |
       b1 Z4 P! d7 |0 I8 e+ \
A. rand formula + j2 B- _1 Z+ C" r) Z. P
B. union shop
1 r" r! m4 B+ A3 Q$ n7 P9 D- SC. closed shop $ \. l/ G5 F. X# P
D. open shop ( p+ B3 z9 x1 I3 B

1 M/ a+ A- t4 c; y' a5 O4 x56. Which statement is true of an employer under a typical collective agreement?. F7 Y  n9 b/ c% R. q
# S. g7 J. \' m) c  [4 {
A. The employer cannot terminate an employee under any circumstances;
7 t; p' `$ L0 K" l- z- FB. The employer can only terminate an employee if he gives reasonable notice;* u* Z5 N, K; E7 `5 m
C. The employer can not lay off an employee because of a downturn in business;- c! \; B: K" B. g* n# z' H0 ~
D. none of the above.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 12:10 | 显示全部楼层
57. Which of the following would likely be confidential information of a contractor, which a construction manager going to a new job should not share with his or her new employer?
& |5 \/ f  n; G; D: i4 ]. o  j, a, k     
& Q3 F& }8 u& |* |; ^' ?, \A.    the price the contractor pays for reinforcement from the major reinforcement supplier in town / I& a! ^6 L* T1 i/ J
B.    the names of the major concrete suppliers in town
. |" [6 v0 {# d" _. P7 hC.    the dates on which the electrical trade closes down for the Christmas break
0 F' b' m0 W9 i1 l" yD.    the date on which tenders are due for a large bridge construction project : k; {7 U* F! f& y! l' C# a' X
8 K: O7 d! A6 B. [) f9 q
58. Which of the following suggests an employment relationship rather than an independent contractor relationship?
) ?& o' E& s* g     
/ R" L, j) K/ j0 I5 NA.    the person performing the work provides all of the tools and materials
+ {  J: e8 L2 |B.    the work is done when it suits the person performing the work
1 A) c: |6 f9 K1 r- p7 zC.    the employer provides detailed instruction on how the work is to be done 4 T8 o% N( e' ]6 ]9 Q# f. [/ \
D.    the rate for doing the work is negotiated for each portion of work
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:12 | 显示全部楼层
同言同羽 置业良晨
59. Zoe is a software engineer and is driving from her office to a client's office. Zoe's car is hit from behind by a polic car. Who can Zoe successfully sue?% o; h, \5 s" z; u# k/ j2 i7 H/ f
% o! F5 h( u6 ]
A. Her employer  X# E* p5 g/ d) a
B. The police officer's employer6 i0 J1 A+ t4 S9 F2 h# ?
C. The police officer
! v* `" K" `) N! d2 F+ v3 e' [9 ZD. None of the above
: Z/ |0 J& H) y% ~- [2 D7 ]' ^  ?* W$ H/ B: Y3 V- Z2 h
60. Which of the following is true regarding occupational health and safety?
: R) o$ q2 _. J$ q    1 |8 R6 t" m+ z/ J
A.  in each province, there are many statutes governing occupational health and safety in different contexts * r$ ^: h% `, n, S) t
B.  federal legislation may set occupational health and safety standards in some contexts 2 B% l2 E5 S; V. d7 {6 J) o
C.  employers are required to ensure safe working conditions
0 B! I' {9 ~1 U& [2 TD.  all of the above
大型搬家
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:36 | 显示全部楼层

下面提供考试真题部分答案:

见附件

1.doc

23.5 KB, 阅读权限: 2, 下载次数: 14

售价: 500 加币现金  [记录]

1-12 题答案

鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 20:55 | 显示全部楼层
61. In what circumstances might an environmental consultant not have to report the findings of their investigation to the regulatory authority? 0 ^0 A' C1 J! ^0 m$ X
     ( Y6 h6 E6 E% T% ?1 E
A.  when the client, and not the regulatory authority, requested the investigation + o1 Y) Q4 n& j" ]. X8 I
B.  when there is a confidentiality agreement with the client
5 Y# E" H% T8 A( I9 H6 a8 S( I5 GC.  there are no such circumstances; reports must always be disclosed % b- J6 U% _' A/ n- `
D.  when the investigation is requested by a lawyer for the purpose of providing legal advice and there is a comprehensively worded confidentiality agreement in the consulting contract 7 D. Z  e2 P1 o$ S2 Q. ]8 ?
3 Q- N$ ?4 o$ G& C# d1 [
62. Which of the following could be an environmental offence?   S4 d4 r7 q, s/ F$ e. L
     . W9 A. Z3 k$ {7 C: e( G( s
A.    failure to take reasonable steps to prevent contamination
, K- p$ _9 ]# P& h) @B.    failure to keep accurate books and records ! n" C7 B+ j" h; J. V$ [
C.    failure to report contamination
# s- l5 ~. F  T' N& E* YD.    all of the above   n) ]- M+ |7 n4 U# ~- a% n* }

5 \# ~2 U0 R7 k. V! o. K2 U63. If a company causes contamination, who may be liable?
/ J0 p5 s" |+ D, ]; A4 M  j& U( S
A. The company itself$ f* P- p; v" h& y% D4 y
B. the directors, U, q1 E6 R- |5 o, K) \  G
C. the prvious landowner9 H$ f1 `- K) N3 \* q: f) ?
D. A and B
理袁律师事务所
鲜花(64) 鸡蛋(0)
发表于 2008-12-25 21:19 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
大型搬家
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 22:07 | 显示全部楼层
64. Privacy legislation protects against the misuse of information about persons and organizations. Which of the following has the least protection under such legislation? , T/ K. H1 S9 Z0 v  W4 J4 S
      6 _: I9 \/ u! {1 y3 S
A.    private citizens / Y; r- L( _8 a. l. u# z
B.    partnerships + X! U, c' ~: C9 ^. b# E7 Y
C.    trade unions % P4 B% \( c/ Z/ ]4 I
D.    corporations

Because corporations have limited liability.doc

23.5 KB, 阅读权限: 2, 下载次数: 11

售价: 100 加币现金  [记录]

原因分析

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 12:33 | 显示全部楼层

thanks.

同言同羽 置业良晨
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 13:40 | 显示全部楼层
同言同羽 置业良晨
65. What must a plaintiff prove in order to prove infringement of copyright on the Internet? ' n) N1 V: F3 V
      
4 H! B1 ?) x5 N' W' g" P* {A.    that the work that was copied was protected by copyright
2 p8 k( N+ i4 h7 pB.    that the defendant actually copied the protected work 2 d6 \) ^& M+ a, Y7 p) R/ p! i; j
C.    that a substantial portion of the work was copied
) T2 T. h& Z5 \& h+ N$ [2 H7 ]D.    all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:15 | 显示全部楼层
66. Which of the following is a correct statement of law?  
& m% ?- O+ O6 i5 k; h, t, |     
/ o7 Z/ [; @. x0 ]A.  standard form contracts always contain both general and special provisions 5 B" X! _9 N0 }# c
B.  courts do not imply terms unless it is necessary to give effect to the intention of the parties
# q3 O; z! m- @( S, ]& X& r* jC.  where there is a conflict between general provisions and special provisions, the general provisions apply
6 h( I$ U- ]; Y7 n% |2 ~  |! ~D.  contracts cannot have supplemental conditions, all conditions must be included in one document
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:54 | 显示全部楼层

下面提供考试真题部分答案:

老杨团队,追求完美;客户至上,服务到位!
见附件

2.doc

26 KB, 阅读权限: 2, 下载次数: 7

售价: 1000 加币现金  [记录]

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 15:49 | 显示全部楼层

回复 85楼 的帖子

can't open these attachments, can you help out?
鲜花(0) 鸡蛋(0)
发表于 2008-12-27 08:56 | 显示全部楼层
啥时候办班?先报个名。
鲜花(0) 鸡蛋(0)
发表于 2008-12-28 12:16 | 显示全部楼层

playball 你发的真当是好东西!

谢谢! 等着你继续发!
鲜花(0) 鸡蛋(0)
发表于 2008-12-29 12:22 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。
+ m7 g  }  v8 z7 d: TAppega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。, W$ L+ y8 w6 F+ U0 T
这些题目可以帮助学习,但不是考题。
- V8 p  g8 y. N' S7 m另外,透露考题是一种违反APEGGA的道德标准的行为。尤其是在道德考试前,每人都要签字的。
& J8 K' H5 N) s7 s  N考试并不难, 只要下一定的功夫,都能通过。# F* a% X& r) ]4 n7 D% t
并且,通过学习,可以了解加拿大的道德观和法律(这是和中国有相当不同之处),会对每一位中国移民工程师有帮助的。0 X; Y& F0 q* ]5 g
大家不要舍本逐末,为了考试而考试,忘了更重要的东西。
鲜花(31) 鸡蛋(0)
发表于 2008-12-30 09:57 | 显示全部楼层
原帖由 LAOZANG 于 2008-12-29 12:22 发表 ( F0 h7 `# c8 @+ `4 k8 M. z
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。4 k( h( b% b) v% [, T" B  N& F. ~
Appega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。- A3 V6 H3 G+ C$ _- O2 M# f
这些题目可以帮助学习,但不 ...
. m# \/ [* @7 E! `( f$ O
您需要登录后才可以回帖 登录 | 注册

本版积分规则

联系我们|小黑屋|手机版|Archiver|埃德蒙顿中文网

GMT-7, 2026-1-25 00:27 , Processed in 0.190001 second(s), 28 queries , Gzip On, APC On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表