埃德蒙顿华人社区-Edmonton China

 找回密码
 注册
楼主: playball

[聊天灌水] 加拿大职业工程师考试--一起切磋

[复制链接]
鲜花(0) 鸡蛋(0)
发表于 2008-12-18 22:11 | 显示全部楼层

回复 60楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
能否将您这些题目的答案也公布一下?多谢
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 16:10 | 显示全部楼层
22. Under which of the following project delivery models does the contractor not have significant incentive to reduce costs? ) f% O: e* z% R6 c4 o. a

$ \+ K# h+ x1 ^* LA.     alliance agreement 1 V2 |! F2 |8 f/ P  s- {8 J
B.     cost-plus contract
, h. q+ j: Z. N: G' xC.     fixed price contract 9 e2 w3 q" @; o& u$ \" w$ e
D.     unit price contract
+ q8 ~  w& Q$ I+ ~$ v, W" V6 y. \
23. For which of the following types of contract would the scope of work clause be most detailed?
) J! A* B# m! C0 U. ?4 k  
4 l5 r. c: G$ x) V* s. r) A& U& KA.    unit price
( Z5 g3 H. g. P$ LB.    fixed price for a design-bid-build project
8 H. f2 Q2 E% U. p6 C- `7 [C.    fixed price for a design-build project
: ]3 _  e4 u# p! u9 t) |  \: UD.    cost-plus & u) y+ ]+ r7 V6 g. m: A
; {* [$ X! p- D
24. What is another name for an exclusion clause? 7 x" j' x& j( {% r0 T. o

- u# G2 Y$ V0 j" N, T  n" JA.     escape clause & W" }1 d" I- E' |3 T  ?
B.    exemption clause
$ ?9 M5 u# r, MC.    all of the above 9 m( m5 y. n) g# Q# B5 G
D.    protective clause
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-19 17:54 | 显示全部楼层

声明

原帖由 Ape 于 2008-12-18 22:11 发表 * [8 Q  B) d- ?* S
能否将您这些题目的答案也公布一下?多谢
' O2 C5 ^! N3 G; h

+ D& G" T; z/ k' M4 \4 h1. 本人发帖的目的是为了帮助大家通过NPPE考试, 旨在落实到行动, 把平凡的工作做精做细, 发扬光大下;
( ^4 W2 H) t5 W; c$ L" _! H
% h5 `9 ^2 p, p$ e5 O. _2. 总共将有100道考试题目帖上来, 作为大家考前摸底; 如果你不能通过这套题目的话, 你还需要继续努力;
1 B6 p3 G% q: i2 q) h" }, e/ \3 g6 y6 [
3. 答案将在最后被帖上来, 供大家参考.
, w2 G% Y) g6 V, {
+ p5 }  Y, W9 ?4 p# t+ N6 \  T  p4. 有的同志, 通过了考试拿到了证书的而又在网上大言不惭的, 也可以重新测试下你的水平, 达到从根本上消除你狂妄的口气.
鲜花(0) 鸡蛋(0)
发表于 2008-12-20 00:00 | 显示全部楼层

回复 63楼 的帖子

老杨团队 追求完美
非常感谢,将一直拜读下去,希望早点见到全部。不过上一次结束时是27题,这次怎么又从22题开始了?且内容同前面同题号的题不一样
- i6 u  [3 E' g: M& t7 F0 x
6 s) M$ C/ ^7 Q/ R7 B不要在意别人怎么说,其实通没通过差距不一定很大,可能就在一两分之间,很多刚考完的人出来说心里没底,只等通知了,有一定的运气成分。当然我们还是要好好准备才是。
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 17:47 | 显示全部楼层
对不起, 序号弄错了, 不能改正了. 接着来:  h7 }1 O  N0 }3 b) i! Y

, Y, V* U. Q7 s& Y7 K- p% G31. Strict liability can be defined as: 3 m2 h: r" G* {: v/ F
  
6 H+ @* L+ @# H& Q' n9 B% oA.    liability flowing from negligence
; x$ P) _1 N% W9 z$ d9 W4 m* aB.    liability for the fault of another , M' j0 _+ E+ ^$ {1 I3 ~
C    liability without fault
3 g# t6 a' s4 c$ q  O6 J+ ^- [D.    none of the above 8 _  Z, M9 {' r* j

0 H$ f8 u/ m3 h( v1 c- R+ W32. Which of the following is pure economic loss? - J0 W1 H/ h( N  e( M: j
1 R6 L& K, U3 B, Z" [3 [  y0 y$ a
A.      the lost profit of a hotel after the power went out because a motorist knocked over a municipal power pole ( J/ S# m- i8 g% r, F
B.      the painting repair cost after a roofing contractor carelessly chips the paint on the walls of the house / K8 L1 |/ Y2 j3 e8 x
C.      the repair costs after a cyclist's bike is damaged by a careless motorist $ _0 X; E, A3 G/ \" j
D.      the medical costs associated with a car accident injury  0 E8 m: g0 |! n7 D0 I( m6 }
9 g# K. V4 j2 D9 Y7 Q. h5 y
33. Which of the following may succeed as a defence to a negligence claim? $ p7 P$ v$ g* H9 d0 v' U
2 ?3 w1 ]( s& s# s6 h
A.      the victim is an illegal immigrant 4 E0 ?) m4 R" x: r; v0 d- j
B.      the defendant met the standard of care required in the circumstances
0 [$ t) n; R4 i( C( n$ L  YC.      the tortfeasor did not intend to cause harm to the victim
1 t  @* V& b, O1 S, x+ AD.      the victim is far wealthier than the tortfeasor
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-20 23:09 | 显示全部楼层
34. A third party to a lawsuit may be added by
5 R& w  M. S$ J5 v( n0 B" A1 o6 p5 y; @
A. either a plaintiff or a defendant6 S$ O; c& f9 ]2 b+ |- \/ Q" o
B. plaintiff
7 |4 X3 Q* x& k. g) ]C. defendant- M3 s( p4 H  r
D. none of above4 P* m1 g* n2 F2 v/ M

4 y6 {2 Y; u9 C( j. ~35. Limitation periods are defined: % F. c& c0 T* J0 `! s7 e

1 L$ s& l2 |5 n6 c+ _- ~) y1 EA.      by the courts as part of the common law
# O2 }" y' S) Y- a/ OB.      only by federal government legislation
# o: Y" N* ]$ Z1 b6 kC.      only by provincial government legislation
# U7 C& V" A: X$ VD.      by federal or provincial government legislation, depending on the subject matter of the limitation period
: D4 v: y0 e4 F& W( P0 z: v9 r- }9 n* h
1 d$ H5 _" \6 p8 L# \36. If a plaintiff was 30 percent responsible for his or her own loss, damages will be reduced by 30 percent. What name is given to the doctrine that imposes this reduction? . b, M5 W3 c/ S5 l: J, i
     
2 I( h2 V' G. [A.     joint liability 1 y2 z0 e  u9 A2 K9 }9 P& `  @5 _
B.     joint and several liability 4 A& H0 @- A0 ]$ H1 A0 }7 o$ @" Z# c
C.     several liability
9 ]$ B& X6 Z  dD.     contributory negligence
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 14:31 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
37. which of the following is not a pleading?+ {% ~$ g' f# x4 l% A

8 T* ?9 o- R# r; M2 X/ w5 JA. A reply
7 T' c2 S" p0 }- e) y( ^2 `# ~B. A statement of defence1 W/ N& w4 \/ w& G. w
C. Discovery of documents
3 |' g) S( f1 t" t' g4 p5 `D. Interrogatories8 d( d! {5 ~( P# z3 Q

( y  d/ U2 J" x% G; i38. What documents do judges examine prior to the commencement of a lawsuit?5 s$ F. J* A7 s/ q  X

7 |9 Q" p0 i# |A. The statement of claim) z8 T1 r1 V# I0 Z1 ^" Y
B. correspondence between the parties
# n6 w% `7 M- x. j% BC. photographs
8 K7 Z* O8 y3 o) e7 HD. settlement offers
3 y. A; g7 r" w- L( T" b4 J+ v2 L, j( _. k& g  F7 W8 r
39. Which is generally the least voluntary method of dispute resolution?
4 D" z% V( \3 K8 J$ Z     
4 E+ W/ a5 J3 k) p$ |) hA.  litigation 4 a/ `( l( @- k5 ~+ x* G: D
B.  negotiation
. T& Z3 f# h' k0 z+ tC.  mediation : E+ h% h* a; _: ^! d
D.  arbitration
. M  }0 Y% Y8 f6 c( {' a" ?2 d( I$ r% W, ~
40. Which of the following methods of dispute resolution offers the advantage of privacy? # s1 C* K  O. ?3 {& ?% s: P( a) z
     $ T7 ^$ M' {5 m/ L2 H
A.  arbitration 4 o& M* l/ C# C# N0 N1 a0 a# u! H
B.  mediation 8 Q0 Z- @1 u5 s/ d( ~
C.  negotiation   Z+ ]2 [5 C7 Y1 u8 u: n
D.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-21 21:05 | 显示全部楼层
41. Which of the following may require further design work by the consultant relatively late in the project? / p/ `2 i" [  L
   
9 e- d* G# V$ q+ t# ]A.  contractor error 8 |0 B# t4 n% J% ?6 J& o
B.  tenant requests
) z( |$ }# l7 K& tC.  unforeseen conditions
1 }4 I5 h& x8 ]  z7 D0 ]0 d. HD.   all of the above
4 \% Y4 K1 L$ L8 D) y  W# F+ ~+ U4 |, R" z; U- \3 q
42. which of the following is not a contractual risk allocation provision?1 D$ I5 P/ H  Q% T
# x) Y9 i, f. T  f, P' m/ c
A. An insurance clause
% |& M# E) ?/ B* R2 P9 {7 }/ [B. An 'unforeseen conditions' clause
: P4 u6 b- V( G& p9 g% q& ~C. A pay-when-paid clause
! `4 ?! U! ?5 y& OD. none of the above
鲜花(0) 鸡蛋(0)
发表于 2008-12-21 23:33 | 显示全部楼层

回复 68楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
感谢。
) g  n0 M: Q1 [7 ]5 u这些是以前考过的真题吗?
8 J/ F6 s5 U6 B) o0 W3 ?& e1 F请继续
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 11:18 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
43. Which of the following may result in loss of insurance coverage?
+ h' ^0 K' ?6 M6 v4 ~- B
! u) u6 ^. q5 Y+ hA.      failure to comply with the notice provisions * t7 [. F! `) ?  A& X" \" i
B.      lack of insurable interest % o6 a: a9 j! z0 p
C.       all of the above 0 h, M3 m3 W0 W8 Q
D.       material non-disclosure
' w' s% |' V9 o1 N8 Y
: c7 k$ |2 E) N1 ~: K44. Which of the following is true?
! O" R% T" r. j
  q% ]- R2 P" Q! LA.      professional liability policies are normally claims-made policies 7 S* \9 e2 S0 B, x4 ?. _! C. \
B.      a claims-made policy covers liability for events that occurred in a specific time period  
6 M3 H  [2 m1 UC.      property insurance policies are either claims-made or occurrence policies
0 Z! N% R% h8 \, g* E5 H6 wD.      none of the above
理袁律师事务所
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-22 14:11 | 显示全部楼层
45. which statement is true in the following:
2 G8 l! a  Y" @4 k- F
* z" t" v2 g1 S. H/ {A. Sub-subcontractor qualify as a claimant under a standard form CCDC labour and material payment bond;
4 K( K- P# o( A7 k5 uB. The limitation periods available to the contractor may not be available to the surety;7 k4 W' _6 ~0 T6 `: R- ~
C. The limitation periods available to the surety may not be available to the principal;
3 D  {% V5 k* JD. labour and material payment bond is not a one-tier bond.& q8 I! l$ k* n: m& K

6 V0 P9 r, D: K: m$ P' N46. Who may be an obligee under a bonding contract?
* V) b. T9 \1 V9 F  p& z( M      
# q1 W1 q( N* u2 ZA.  the general contractor % U+ T; o% V7 W6 W- D$ [/ j
B.  a private owner   }4 Z7 \! o. P: F+ ]5 N! ?+ A. z8 v
C.  the government & |9 V) O# m8 K$ g; V& P# }$ [4 {5 T
D.  all of the above 3 ~/ f" I6 ?( h$ ?& B( b) F9 W
" D, ]1 v$ G) d" N, ^, l7 q1 [
47. A bidder bid $80 and then refused to enter into a contract with the owner. The other three bidders bid $88, $90, and $100. The owner accepted the $90 bid. The face value of the bid bond was $9. How much is the surety required to pay the owner?  : |0 r7 ?( A! {# }5 \* K
    6 D* _4 T3 r* }/ m" i/ ^- A. r
A.  $20
) \0 e" O7 o  F1 ~1 eB.   $9
- g/ |8 R" t, k5 n2 P2 i1 _) jC.   $8
% \* |1 U$ A. I& i0 rD.   $10
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 09:58 | 显示全部楼层
48. Which parties may be potentially liable for a breach of trust under a Construction Lien Act?* i4 Y+ \/ T4 W( F+ `8 ^& x

+ v5 j! u$ _  u; G$ OA. Owner
# h$ f  X' F9 R/ I& _3 HB. contractor
( m+ ]2 N/ Z* NC. worker; k8 b6 z# a* d! l
D. material supplier. p0 @/ O/ a  u+ J* f, L5 b

- W- D. n( N# o0 S0 @$ s* a+ z. f0 n49. Against what property does the lien holder have a cause of action? : y& U' j& `4 K8 _6 S
      
. j* `1 h1 N5 J5 ^A.    the interest that the party the lien holder contracted with has in the property on which the work was done
$ P- d. J- _' L2 [B.    the property owned by the party the lien holder contracted with ) m- I  ^# z* s. t% i' R7 U0 [
C.    the property on which the work was done " j, N4 L; h; a8 m5 U0 x' n
D.    none of the above " o! Z) H$ J  [% C- x1 D& z
( y! J* c( W, h" j- ^
50. An owner providing substitute security for a lien is, in effect:  9 G2 E) m1 @0 z
     0 v! u$ b# ?: b! O; @2 N7 w
A.  reducing his chances of having to pay out on the lien # k" W& s; r$ k1 U6 y0 y
B.  not changing the likelihood of having to pay the lien amount
9 Q) p) |* k" W& k! MC.  admitting liability for the lien ' ^3 D. _. h4 F9 Q. m) F; J! U
D.  none of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-23 13:59 | 显示全部楼层
同言同羽 置业良晨
51. What is the key weakness of bar charts as a scheduling tool? # [/ B$ Y* m: X2 t: Y$ @
      
) U( Z7 a4 H5 LA.  they are hard to understand
% V/ Q/ Z2 d( h8 cB.  they take a long time to produce 9 T" }" U6 b8 T: e* s
C.  they do not show an inter-relationship between activities
. |7 m# h2 \& F; S( P7 x5 pD.  it is often impractical to estimate the time a particular task will take / a+ H6 Y+ Q* j

$ @+ x, ?9 b* M: d$ Z' x) c52. Which of the following elements of a delay claim is generally the most difficult to prove? ) E9 G/ e1 S! E- n
      ) C% g! z; [/ D: I  d6 y4 T2 Q6 C
A.  the amount of additional cost caused by the delay, or acceleration 7 K6 R! Q6 `; f6 ^& O, S
B.  duty to not interfere with the other party's performance of the contract + {2 u6 l  k+ y3 `; h* ?# G" h
C.  breach of the duty to not interfere ' g- k' ~; Y6 j% H
D.  that the breach of duty caused a delay, or a need for acceleration
, t. I) m) N, _. k! `6 A
- M1 r7 m1 y5 |. U5 F0 u2 x53. Which of the following statement is true in a standard CCDC2 contract?7 T7 B+ {$ v& e1 Q+ n' }- g3 m3 m
- `% O& ^+ c5 h. O6 p  F! n5 R
A. A compensable delay is not excusable( S! E7 S! D# U, G+ F( ^
B. A contractor-caused delay is compensable
0 W6 X; f; \5 j8 |2 J+ Z! }: D! WC. A contractor-caused delay is not excusable6 |" C3 b+ X8 T0 d- o1 ]5 |  w: Y
D. Critical path activities are those in a sequence that must individually be completed before the next activity can begin.
鲜花(0) 鸡蛋(0)
发表于 2008-12-23 21:13 | 显示全部楼层

回复 73楼 的帖子

老杨团队,追求完美;客户至上,服务到位!
good job. a lot of questions for practice laws.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-24 22:35 | 显示全部楼层
54. Which of the following is not true regarding an employer-dependent contractor relationship? $ S8 }/ W7 v  i( B3 G
      / V) n( g" T) ^8 T
A.  the contractor may use his or her own tools
8 d0 }7 H% ?8 e/ S; j# JB.  the contractor is generally not trained by the employer
: x* q1 t) E  U6 xC.  the contractor will generally set his or her own work hours
+ `. s7 V) i( O. s: c0 uD.  the contractor is generally economically independent from the employer ; ~( p7 Y2 P1 ^  [

+ v* w3 }! J4 R4 o5 K7 U55. What term describes the situation in which workers are required to pay union dues but not compelled to join the union?
" a# n6 |4 N! Z; v% o     
6 z8 y$ Z3 I4 ?  n+ uA. rand formula 8 ]1 J; {, w0 s& |( C. C
B. union shop $ N! H4 V( Q; O. v% R
C. closed shop
1 n5 M$ s3 |+ X+ B/ z0 vD. open shop % Y! `& ]/ s0 Z& K/ }

5 d& U& Q0 M& X+ O' L3 m; F56. Which statement is true of an employer under a typical collective agreement?
) @) `5 E* B( C, M1 r% E: e2 E" S6 l. y9 g& O% l; M# A- u! Y' ]  m
A. The employer cannot terminate an employee under any circumstances;& Y% z( x. z& W+ o- }
B. The employer can only terminate an employee if he gives reasonable notice;
8 P: G; R" z( K4 u3 D% WC. The employer can not lay off an employee because of a downturn in business;
) K* l' N* [/ D9 vD. none of the above.
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 12:10 | 显示全部楼层
57. Which of the following would likely be confidential information of a contractor, which a construction manager going to a new job should not share with his or her new employer? ; }9 q' M0 I1 A6 E. Y$ _6 L& H. q
     
: B& A) u* r5 N0 ~; BA.    the price the contractor pays for reinforcement from the major reinforcement supplier in town
4 v5 q& H, R9 H% J( M( H, l/ EB.    the names of the major concrete suppliers in town ( r/ G5 O/ Y* G0 T
C.    the dates on which the electrical trade closes down for the Christmas break
2 E" _& e1 M2 E" G1 qD.    the date on which tenders are due for a large bridge construction project
  V" {/ L  ~3 B2 p' ?6 F
) T. \2 v9 O+ c7 T7 w58. Which of the following suggests an employment relationship rather than an independent contractor relationship? ) P9 b. w0 N$ ^5 x0 _
     ) v7 d# e/ Z" L. n# I
A.    the person performing the work provides all of the tools and materials ' X6 H6 \" Y( e
B.    the work is done when it suits the person performing the work
3 B9 N/ A8 T+ D) y/ WC.    the employer provides detailed instruction on how the work is to be done 5 q0 r, ~( s' J- h" |2 C
D.    the rate for doing the work is negotiated for each portion of work
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:12 | 显示全部楼层
同言同羽 置业良晨
59. Zoe is a software engineer and is driving from her office to a client's office. Zoe's car is hit from behind by a polic car. Who can Zoe successfully sue?5 e3 g/ ~2 z4 g1 t: Z$ e4 @
% X0 e3 J% A& b# y
A. Her employer
  s- B) X8 N3 r4 W9 G3 K& `% GB. The police officer's employer
1 b8 Y; {  E5 G' X& k9 i4 IC. The police officer
' S, S3 W( C7 B6 C7 AD. None of the above
4 I4 `/ y/ V) I* u9 H& Z+ c
! L% J" ]5 U' {3 ]3 a1 N9 }4 l60. Which of the following is true regarding occupational health and safety?
! Z5 M! m7 r( n+ t/ p2 c. x6 M& K3 U    & J) B& h1 L3 ]/ m
A.  in each province, there are many statutes governing occupational health and safety in different contexts ; c1 x2 X; B' K( p0 I" K
B.  federal legislation may set occupational health and safety standards in some contexts
1 i* f4 a( V: p- m+ e4 gC.  employers are required to ensure safe working conditions ) T' N' H8 s( o' p! H
D.  all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 14:36 | 显示全部楼层

下面提供考试真题部分答案:

见附件

1.doc

23.5 KB, 阅读权限: 2, 下载次数: 14

售价: 500 加币现金  [记录]

1-12 题答案

鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 20:55 | 显示全部楼层
61. In what circumstances might an environmental consultant not have to report the findings of their investigation to the regulatory authority?   @0 e/ Q( n2 x, n% ^
     . w8 j& q; E" D  t
A.  when the client, and not the regulatory authority, requested the investigation
( s$ o1 _) h, b) p+ @* A0 xB.  when there is a confidentiality agreement with the client 4 k& Y, v% ~7 m: J( _9 G9 u5 i
C.  there are no such circumstances; reports must always be disclosed ) t4 `9 R0 r; @: F3 d
D.  when the investigation is requested by a lawyer for the purpose of providing legal advice and there is a comprehensively worded confidentiality agreement in the consulting contract ( F1 T0 A  t, X& _' e+ a& Q4 }

8 t/ `' D4 O+ `- N; j62. Which of the following could be an environmental offence?
" x2 n( ?1 g, B0 u. ^4 S     
3 W% v, H; L7 m* \6 j9 v" P$ ]A.    failure to take reasonable steps to prevent contamination * w$ s- G/ {6 X6 R4 x
B.    failure to keep accurate books and records ; d2 e7 r% _0 E  K9 [
C.    failure to report contamination 0 N, s9 E, ?7 J4 V2 h/ d
D.    all of the above * D3 o* u$ ^: J. h
( u( m: q) z' a' G. h3 h1 t  Z
63. If a company causes contamination, who may be liable?; x8 T9 \/ @3 Q. a8 o0 k4 |
- u; ~% ~6 y4 U6 P/ N' [8 F
A. The company itself
5 w) U& r  n' T2 Q/ |( G# A' oB. the directors
8 Z7 }8 B" R$ Q  jC. the prvious landowner" c' M# p. e/ |5 N7 B3 z
D. A and B
鲜花(64) 鸡蛋(0)
发表于 2008-12-25 21:19 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-25 22:07 | 显示全部楼层
64. Privacy legislation protects against the misuse of information about persons and organizations. Which of the following has the least protection under such legislation?
" j' n: Y( y9 R/ L5 y' N      
$ B% ?& |- S7 g" M, R2 dA.    private citizens - Q9 t( |- K, l! n4 w& D" H# t
B.    partnerships 7 z% C, n- ]1 ~( b& M, j1 J. e- k3 ^8 E
C.    trade unions " t2 k/ f' {: l5 ^( p7 k
D.    corporations

Because corporations have limited liability.doc

23.5 KB, 阅读权限: 2, 下载次数: 11

售价: 100 加币现金  [记录]

原因分析

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 12:33 | 显示全部楼层

thanks.

同言同羽 置业良晨
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 13:40 | 显示全部楼层
同言同羽 置业良晨
65. What must a plaintiff prove in order to prove infringement of copyright on the Internet? 3 ?  J2 M; }# m
      $ ]* d1 H! s- U& L- Q
A.    that the work that was copied was protected by copyright   t! T* M* O" y1 S" y. Y
B.    that the defendant actually copied the protected work * _+ |8 @* P8 `3 m4 s
C.    that a substantial portion of the work was copied ; G9 [$ }: g' c8 N) ~- m
D.    all of the above
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:15 | 显示全部楼层
66. Which of the following is a correct statement of law?  ) P5 \; `& X6 k
     
' _6 f1 J" N$ ?1 v$ N/ T; d6 OA.  standard form contracts always contain both general and special provisions
. F) D) D7 C( }" t0 a$ b- }2 [4 H1 OB.  courts do not imply terms unless it is necessary to give effect to the intention of the parties 0 e) X+ |# T& r) y
C.  where there is a conflict between general provisions and special provisions, the general provisions apply
  i" a* V: m( }2 h3 E' N* FD.  contracts cannot have supplemental conditions, all conditions must be included in one document
鲜花(1) 鸡蛋(0)
 楼主| 发表于 2008-12-26 14:54 | 显示全部楼层

下面提供考试真题部分答案:

老杨团队,追求完美;客户至上,服务到位!
见附件

2.doc

26 KB, 阅读权限: 2, 下载次数: 7

售价: 1000 加币现金  [记录]

鲜花(0) 鸡蛋(0)
发表于 2008-12-26 15:49 | 显示全部楼层

回复 85楼 的帖子

can't open these attachments, can you help out?
鲜花(0) 鸡蛋(0)
发表于 2008-12-27 08:56 | 显示全部楼层
啥时候办班?先报个名。
鲜花(0) 鸡蛋(0)
发表于 2008-12-28 12:16 | 显示全部楼层

playball 你发的真当是好东西!

谢谢! 等着你继续发!
大型搬家
鲜花(0) 鸡蛋(0)
发表于 2008-12-29 12:22 | 显示全部楼层
老杨团队,追求完美;客户至上,服务到位!
看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。8 h" u% w$ x. c/ \
Appega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。+ K  ?- z9 j$ w1 j: w0 r8 F" ]
这些题目可以帮助学习,但不是考题。
# Y+ {/ m  x1 j3 D0 R5 S, s9 Y% K, L; X另外,透露考题是一种违反APEGGA的道德标准的行为。尤其是在道德考试前,每人都要签字的。
4 W9 y" x; m- i9 W考试并不难, 只要下一定的功夫,都能通过。, s0 l5 z3 S; f* t  U/ M
并且,通过学习,可以了解加拿大的道德观和法律(这是和中国有相当不同之处),会对每一位中国移民工程师有帮助的。% {) O" m( V: {: Z& D& ]
大家不要舍本逐末,为了考试而考试,忘了更重要的东西。
鲜花(31) 鸡蛋(0)
发表于 2008-12-30 09:57 | 显示全部楼层
原帖由 LAOZANG 于 2008-12-29 12:22 发表
7 b* Z2 J7 t0 [: o看了playball发上来的题目,不知道他/她是从哪里搞来的?感觉和APEGGA考试的题不是一道局。
5 P4 M% W) O  D1 M1 I0 p2 SAppega比较注重案例分析,这些是建立在理解书中的理论的基础上,而不是考试书中的条条框框。
9 u$ n4 g- m; W这些题目可以帮助学习,但不 ...

# v) o/ t6 H2 z8 @; ^
您需要登录后才可以回帖 登录 | 注册

本版积分规则

联系我们|小黑屋|手机版|Archiver|埃德蒙顿中文网

GMT-7, 2025-11-23 21:58 , Processed in 0.205152 second(s), 28 queries , Gzip On, APC On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表